EB-2012-0173
|
dec_order_cost awards_Welland Hydro_20130528
|
Decision and Order on Cost Awards
|
2013-05-28
|
|
2013-05-28
|
EB-2012-0173
|
VECC_Cost Claim_Welland_20130422
|
Cost Claim
|
2013-04-19
|
2013-04-22
|
2013-04-19
|
EB-2012-0173
|
Energy Probe_Costs Claim_Welland Hydro_20130419
|
Cost Claim
|
2013-04-18
|
2013-04-19
|
2013-04-18
|
EB-2012-0173
|
VECC cost claim extension request_20130414
|
Correspondence
|
|
2013-04-14
|
2013-04-14
|
EB-2012-0173
|
OEB Reply_VECC cost claim extension request_20130416
|
Correspondence
|
2013-04-16
|
|
2013-04-16
|
EB-2012-0173
|
Welland_VECC Cost Claim Extension_20130415
|
Correspondence
|
|
2013-04-15
|
2013-04-15
|
EB-2012-0173
|
VECC_Cost Claim Extention Req_Welland_20130415
|
Correspondence
|
2013-04-12
|
2013-04-15
|
2013-04-12
|
EB-2012-0173
|
rate_order_WellandHydro_20130411
|
Rate Order
|
2013-04-11
|
|
2013-04-11
|
EB-2012-0173
|
BdStaff_SUB_Welland Hydro_20130328
|
Submission
|
2013-03-28
|
|
2013-03-28
|
EB-2012-0173
|
Welland_Response_20130402.pdf
|
Submission
|
|
2013-04-02
|
2013-04-02
|
EB-2012-0173
|
SEC_CostClaim_Welland 2013 Rates_20130326.pdf
|
Cost Claim
|
|
2013-03-26
|
2013-03-26
|
EB-2012-0173
|
dec_order_WellandHydro_20130321
|
Decision and Order
|
2013-03-21
|
|
2013-03-21
|
EB-2012-0173
|
WELLAND_2013 RTSR MODEL_20130219.xlsm
|
Settlement Proposal
|
|
2013-02-19
|
2013-02-19
|
EB-2012-0173
|
WELLAND_2013 EDDVAR_20130219.xlsm
|
Settlement Proposal
|
|
2013-02-19
|
2013-02-19
|
EB-2012-0173
|
Welland_2013 COP Forecast_20130219.xlsx
|
Settlement Proposal
|
|
2013-02-19
|
2013-02-19
|
EB-2012-0173
|
Welland_2013 Chapter 2 Appendices_20130219 .xlsm
|
Settlement Proposal
|
|
2013-02-19
|
2013-02-19
|
EB-2012-0173
|
Welland_ RRWF_20130219.xlsm
|
Settlement Proposal
|
|
2013-02-19
|
2013-02-19
|
EB-2012-0173
|
Welland Hydro 2013 Load Forecast_Without CDM Adj_20130219.xls
|
Settlement Proposal
|
|
2013-02-19
|
2013-02-19
|
EB-2012-0173
|
Welland Hydro 2013 Load Forecast_20130219.xls
|
Settlement Proposal
|
|
2013-02-19
|
2013-02-19
|
EB-2012-0173
|
Welland 2013_Cost_Allocation_Model_V3_Direct Allocation_20130219.xlsm
|
Settlement Proposal
|
|
2013-02-19
|
2013-02-19
|
EB-2012-0173
|
Welland_Settlement Agreement_20130219.pdf
|
Settlement Proposal
|
|
2013-02-19
|
2013-02-19
|
EB-2012-0173
|
Welland_Supplemental IRR Response_Appendix C_20130130.pdf
|
Interrogatory Response from Applicant
|
|
2013-01-30
|
2013-01-30
|
EB-2012-0173
|
Welland_Supplemental IRR Response_Appendix B_201301310.pdf
|
Interrogatory Response from Applicant
|
|
2013-01-30
|
2013-01-30
|
EB-2012-0173
|
Welland_Supplemental IRR Response_Appendix A_20130130.pdf
|
Interrogatory Response from Applicant
|
|
2013-01-30
|
2013-01-30
|
EB-2012-0173
|
Welland_Supplemental IRR Response_20130130.pdf
|
Interrogatory Response from Applicant
|
|
2013-01-30
|
2013-01-30
|
EB-2012-0173
|
Welland Hydro 2013 Load Forecast Board Staff 52b_20130130.xls
|
Interrogatory Response from Applicant
|
|
2013-01-30
|
2013-01-30
|
EB-2012-0173
|
Welland Hydro 2013 Load Forecast Board Staff 22c_20130130.xls
|
Interrogatory Response from Applicant
|
|
2013-01-30
|
2013-01-30
|
EB-2012-0173
|
Welland Energy Probe 30E RRWF_20130130.xlsm
|
Interrogatory Response from Applicant
|
|
2013-01-30
|
2013-01-30
|
EB-2012-0173
|
Welland Energy Probe 30B RRWF_20130130.xlsm
|
Interrogatory Response from Applicant
|
|
2013-01-30
|
2013-01-30
|
EB-2012-0173
|
2011 Final Annual Report Data_Welland Hydro-Electric System Cor_20120130..xlsx
|
Interrogatory Response from Applicant
|
|
2013-01-30
|
2013-01-30
|
EB-2012-0173
|
VECC_IR_Supplental_Welland_20130117
|
Interrogatories to Applicant
|
|
2013-01-17
|
2013-01-17
|
EB-2012-0173
|
Bd_Staff_Supp_IR_Welland_20130117
|
Interrogatories to Applicant
|
2013-01-17
|
2013-01-17
|
2013-01-17
|
EB-2012-0173
|
BdStaff_Supp_IR_Covltr_Welland_20130117
|
Interrogatories to Applicant
|
2013-01-17
|
2013-01-17
|
2013-01-17
|
EB-2012-0173
|
SEC_ IR_Supplementary_20130116
|
Interrogatories to Applicant
|
|
2013-01-16
|
2013-01-16
|
EB-2012-0173
|
Energy Probe Supplemental IRs Welland Hydro_20130111
|
Interrogatories to Applicant
|
|
2013-01-11
|
2013-01-11
|
EB-2012-0173
|
Energy Probe Supplemental IRs to Welland Hydro Ltr OEB_20130111
|
Interrogatories to Applicant
|
|
2013-01-11
|
2013-01-11
|
EB-2012-0173
|
po3_Welland_20130110
|
Procedural Order
|
2013-01-10
|
|
2013-01-10
|
EB-2012-0173
|
2011 4th Quarter OPA Results_20121221.pdf
|
Interrogatory Response from Applicant
|
|
2012-12-21
|
2012-12-21
|
EB-2012-0173
|
2006-2010 Final OPA CDM Results.Welland Hydro-Electric System Corp_20121221..xls
|
Interrogatory Response from Applicant
|
|
2012-12-21
|
2012-12-21
|
EB-2012-0173
|
Welland_IRR Response_20121221.pdf
|
Interrogatory Response from Applicant
|
|
2012-12-21
|
2012-12-21
|
EB-2012-0173
|
po2_Welland_20121220
|
Procedural Order
|
2012-12-20
|
|
2012-12-20
|
EB-2012-0173
|
Welland_Extension Request_20121219.pdf
|
Correspondence
|
|
2012-12-19
|
2012-12-19
|
EB-2012-0173
|
SEC_IR_WellandHydro_20121129
|
Interrogatories to Applicant
|
|
2012-11-30
|
2012-11-30
|
EB-2012-0173
|
VECC_IR_Welland_20121129
|
Interrogatories to Applicant
|
|
2012-11-29
|
2012-11-29
|
EB-2012-0173
|
Bd_Staff_IR_Welland_20121126
|
Interrogatories to Applicant
|
2012-11-27
|
2012-11-27
|
2012-11-27
|
EB-2012-0173
|
BdStaff_IR_Covltr_Welland_20121126
|
Interrogatories to Applicant
|
2012-11-27
|
2012-11-27
|
2012-11-27
|
EB-2012-0173
|
Energy Probe_IR_Welland + Ltr OEB_20121127
|
Interrogatories to Applicant
|
|
2012-11-26
|
2012-11-26
|
EB-2012-0173
|
po1_Welland_20121112
|
Procedural Order
|
2012-11-12
|
|
2012-11-12
|
EB-2012-0173
|
EB-2012-0173 Welland Hydro-Electric System Corp. - PROCEDURAL ORDER No. 1
|
Procedural Order
|
2012-11-12
|
|
2012-11-12
|
EB-2012-0173
|
WELLAND_AFFIDAVIT_INTERVENORS_20121101.pdf
|
Affidavits of Service
|
|
2012-11-01
|
2012-11-01
|
EB-2012-0173
|
VECC_INT_REQ_Welland_20121029
|
Intervenor Request Letter
|
|
2012-10-29
|
2012-10-29
|
EB-2012-0173
|
SEC_INT_REQ_20121024.pdf
|
Intervenor Request Letter
|
|
2012-10-24
|
2012-10-24
|
EB-2012-0173
|
WELLAND_Affidavit_Publication_20121024.pdf
|
Affidavits of Service
|
|
2012-10-24
|
2012-10-24
|
EB-2012-0173
|
Energy Probe_INT_REQ_20121018
|
Intervenor Request Letter
|
|
2012-10-18
|
2012-10-18
|
EB-2012-0173
|
noah_Welland_FR_20121015
|
Notice of Application and Notice of Hearing
|
2012-10-15
|
|
2012-10-15
|
EB-2012-0173
|
noah_Welland_20121015
|
Notice of Application and Notice of Hearing
|
2012-10-15
|
|
2012-10-15
|
EB-2012-0173
|
lod_noah_Welland_20121015
|
Letter of Direction
|
2012-10-15
|
|
2012-10-15
|
EB-2012-0173
|
WELLAND_APPL_ADDENDUM_20121009.pdf
|
Application and Evidence
|
|
2012-10-09
|
2012-10-09
|
EB-2012-0173
|
WELLAND_APPL_SEC B 3-4_Rev_20121002.pdf
|
Application and Evidence
|
|
2012-10-02
|
2012-10-02
|
EB-2012-0173
|
WELLAND_2013_Load Forecast_20121002.xlsm
|
Application and Evidence
|
|
2012-10-02
|
2012-10-02
|
EB-2012-0173
|
WELLAND_APPL_SEC C 5-9_Rev_20121002.pdf
|
Application and Evidence
|
|
2012-10-02
|
2012-10-02
|
EB-2012-0173
|
WELLAND_APPL_SEC B 3-4_Rev_20121002.pdf
|
Application and Evidence
|
|
2012-10-02
|
2012-10-02
|
EB-2012-0173
|
WELLAND_APPL_SEC A 1-2_Rev_20121002.pdf
|
Application and Evidence
|
|
2012-10-02
|
2012-10-02
|
EB-2012-0173
|
Ack_ltr_Corresp_Incomplete_Welland_201201002
|
Correspondence
|
2012-10-02
|
2012-10-02
|
2012-10-02
|
EB-2012-0173
|
ack_ltr_Welland_20120911
|
Acknowledgement Letter
|
2012-09-11
|
|
2012-09-11
|
EB-2012-0173
|
WELLAND_APPL_SEC C 5-9_20120830
|
Application and Evidence
|
|
2012-08-30
|
2012-08-30
|
EB-2012-0173
|
WELLAND_APPL_SEC B 3-4_20120830
|
Application and Evidence
|
|
2012-08-30
|
2012-08-30
|
EB-2012-0173
|
WELLAND_2013_Rev_Reqt_Work_Form_V3_20120830
|
Application and Evidence
|
|
2012-08-30
|
2012-08-30
|
EB-2012-0173
|
WELLAND_2013_Cost_Allocation_Model_V3 - Direct Allocation_20120830
|
Application and Evidence
|
|
2012-08-30
|
2012-08-30
|
EB-2012-0173
|
WELLAND_2013 RTSR MODEL_V3_20120830
|
Application and Evidence
|
|
2012-08-30
|
2012-08-30
|
EB-2012-0173
|
WELLAND_2013 PILs Workform_V2_20120830
|
Application and Evidence
|
|
2012-08-30
|
2012-08-30
|
EB-2012-0173
|
WELLAND_2013 EDDVAR_V2_20120830
|
Application and Evidence
|
|
2012-08-30
|
2012-08-30
|
EB-2012-0173
|
WELLAND_ 2013 Chapter2 Appendices_V1.1_20120830
|
Application and Evidence
|
|
2012-08-30
|
2012-08-30
|
EB-2012-0173
|
WELLAND_APPL_COVER LETTER_20120830
|
Application and Evidence
|
|
2012-08-30
|
2012-08-30
|
EB-2012-0173
|
WELLAND_APPL_SEC A 1-2_20120830
|
Application and Evidence
|
|
2012-08-30
|
2012-08-30
|