Message: D08-36859

From: Shelly-Anne Connell
To: Gordon Kaiser, Cathy Spoel, Martine Band, Robert Caputo
Cc:
Sent: 2008-10-08 at 11:41 AM
Received: 2008-10-08 at 11:41 AM
Subject: FW: EB-2008-0264 - Union Gas - East Windsor

Please see the email below.



Shelly

_____

From: BoardSec
Sent: October 8, 2008 11:17 AM
To: Shelly-Anne Connell
Subject: FW: EB-2008-0264







______________________

John Pickernell

Assistant Board Secretary

Ontario Energy Board

416-440-7605

Fax: 416-440-7656

Website: www.oeb.gov.on.ca

Official Correspondence: BoardSec@oeb.gov.on.ca



Address:

P.O. Box 2319

2300 Yonge Street 27th Floor

Toronto, ON

M4P 1E4

______________________





_____

From: Chris Ripley [mailto:CRipley@spectraenergy.com]
Sent: October 7, 2008 5:45 PM
To: BoardSec
Cc: Robert Caputo; Annabelle Ancheta; Chris Ripley
Subject: EB-2008-0264



Union filed a storage application for East Windsor Cogeneration and the Board assigned docket EB-2008-0264.



The T1 contract between East Windsor Cogeneration (“EWC”) and Union is for a 20 year term to align with the 20 year Combined Heat and Power contract signed by EWC with the Ontario Power Authority.



The original T1 contract, signed on August 17, 2007 provided for 100,000 GJ of storage space and deliverability of 1,200 GJ/day (equal to 1.2% of the space). Following the Storage Allocation decision (EB-2007-0725), the storage space allocation was amended to 122,490 GJ. The deliverability was not amended at this time as further analysis of plant operations was required by EWC. The final deliverability number will be calculated in accordance with the Storage Allocation decision.



If you have any questions please contact me.





Chris.





Chris Ripley
Manager, Regulatory Applications
cripley@uniongas.com
Office (519) 436-5476
Cell (519) 365-0450