Search Results for: Records - Case Number=EB-2009-0377 - 57 Records Found
The document result list has reached its limit of 10,000 records. Please refine your search criteria to view more records.
Sorting Your Search Results
The most recent documents automatically show at the top. To sort by different categories (e.g. by Document Type) click the column header. Click it again to switch between ascending/descending order.
Case Information
Click the case number to view details for that proceeding.
Case Number | File Name | Document Type | Applicant | Issued By OEB | Received By OEB | Date Issued/Received |
---|---|---|---|---|---|---|
EB-2009-0377 | SUB_Update to Board_CMSC Recommendations_20100610 | Submission | Independent Electricity System Operator - IESO | 2010-10-06 | 2010-10-06 | |
EB-2009-0377 | Dec_Order_OnCost Award_IESO Fees_20100617 | Decision and Order on Cost Awards | Independent Electricity System Operator - IESO | 2010-06-17 | 2010-06-17 | |
EB-2009-0377 | SUB_Update to Board_CMSC recommendations_EB 2009 0377_ June 2010 | Submission | Independent Electricity System Operator - IESO | 2010-06-09 | 2010-06-09 | |
EB-2009-0377 | IESO_Update to Board_CMSC recommendation_20100526 | Submission | Independent Electricity System Operator - IESO | 2010-05-20 | 2010-05-20 | |
EB-2009-0377 | SUB_Update to Board_CMSC recommendations_May 20 2010 | Correspondence | Independent Electricity System Operator - IESO | 2010-05-20 | 2010-05-20 | |
EB-2009-0377 | IESO_LTR _Comment on Decision_20100409 | Correspondence | Independent Electricity System Operator - IESO | 2010-04-09 | 2010-04-09 | |
EB-2009-0377 | dec_order_IESO_20100401 | Decision and Order | Independent Electricity System Operator - IESO | 2010-04-01 | 2010-04-01 | |
EB-2009-0377 | Transcript_Hearing_March 30_Settlement Proposal_20100330 | Transcripts | Independent Electricity System Operator - IESO | 2010-03-30 | 2010-03-30 | |
EB-2009-0377 | IESO_Sub_Revised support of Settlement P_20100329 | Submission | Independent Electricity System Operator - IESO | 2010-03-26 | 2010-03-26 | |
EB-2009-0377 | IESO_SUB_In support of Settlement P_20100323 | Submission | Independent Electricity System Operator - IESO | 2010-03-23 | 2010-03-23 | |
EB-2009-0377 | PO2_IESO_20100316 | Procedural Order | Independent Electricity System Operator - IESO | 2010-03-16 | 2010-03-16 | |
EB-2009-0377 | IESO_Settlement P_for Approval_20100302 | Settlement Proposal | Independent Electricity System Operator - IESO | 2010-03-02 | 2010-03-02 | |
EB-2009-0377 | IESO_Response_Bdstaff_20100226 | Submission | Independent Electricity System Operator - IESO | 2010-02-25 | 2010-02-25 | |
EB-2009-0377 | IESO_Undertaking Response_Bdstaff_20100226 | Undertaking Responses | Independent Electricity System Operator - IESO | 2010-02-23 | 2010-02-23 | |
EB-2009-0377 | IESO_Response_Bdstaff_20100222 | Submission | Independent Electricity System Operator - IESO | 2010-02-22 | 2010-02-22 | |
EB-2009-0377 | Transcript_REVISED_ IESO_TC_20100211 | Transcripts | Independent Electricity System Operator - IESO | 2010-02-11 | 2010-02-11 | |
EB-2009-0377 | Exhibit& Undertaking List_Tech conference_20100130 | Exhibits | Independent Electricity System Operator - IESO | 2010-02-09 at 3:14 PM | ||
EB-2009-0377 | IESO_Ltr_Transcript correction_20100202 | Correspondence | Independent Electricity System Operator - IESO | 2010-02-02 | 2010-02-02 | |
EB-2009-0377 | Exh TC-8_Techconf_20100129 | Exhibits | Independent Electricity System Operator - IESO | 2010-01-29 | 2010-01-29 | |
EB-2009-0377 | Exh TC-7_Techconf_20100129 | Exhibits | Independent Electricity System Operator - IESO | 2010-01-29 | 2010-01-29 | |
EB-2009-0377 | Exh TC-6_Techconf_20100129 | Exhibits | Independent Electricity System Operator - IESO | 2010-01-29 | 2010-01-29 | |
EB-2009-0377 | Exh TC-5_Techconf_20100129 | Exhibits | Independent Electricity System Operator - IESO | 2010-01-29 | 2010-01-29 | |
EB-2009-0377 | Exh TC-4_Techconf_20100129 | Exhibits | Independent Electricity System Operator - IESO | 2010-01-29 | 2010-01-29 | |
EB-2009-0377 | Exh TC-3_Techconf_20100129 | Exhibits | Independent Electricity System Operator - IESO | 2010-01-29 | 2010-01-29 | |
EB-2009-0377 | Exh TC-2_Tech Conf_20100129 | Exhibits | Independent Electricity System Operator - IESO | 2010-01-29 | 2010-01-29 | |
EB-2009-0377 | Exh TC-1_Tech conference_20100129 | Exhibits | Independent Electricity System Operator - IESO | 2010-01-29 | 2010-01-29 | |
EB-2009-0377 | Exh TC-9 | Exhibits | Independent Electricity System Operator - IESO | 2010-01-29 | 2010-01-29 | |
EB-2009-0377 | Transcript_IESO_TECH_CONF_20100129 | Transcripts | Independent Electricity System Operator - IESO | 2010-01-29 | 2010-01-29 | |
EB-2009-0377 | AMPCO_IRs_IESO_20100129 | Interrogatories to Applicant | Independent Electricity System Operator - IESO | 2010-01-28 | 2010-01-28 | |
EB-2009-0377 | IESO_Prefiled_Evidence_20100129 | Submission | Independent Electricity System Operator - IESO | 2010-01-28 | 2010-01-28 | |
EB-2009-0377 | OPG_CVRLTR_Questions_IESO_20100127 | Correspondence | Independent Electricity System Operator - IESO | 2010-01-27 | 2010-01-27 | |
EB-2009-0377 | OPG_Questions_IESO_20100127 | Correspondence | Independent Electricity System Operator - IESO | 2010-01-27 | 2010-01-27 | |
EB-2009-0377 | VECC_Questions_IESO_TEch Conf_20100125 | Correspondence | Independent Electricity System Operator - IESO | 2010-01-25 | 2010-01-25 | |
EB-2009-0377 | IESO_LTR_TECHCONF_20100119 | Correspondence | Independent Electricity System Operator - IESO | 2010-01-19 | 2010-01-19 | |
EB-2009-0377 | AMPCo_ contact update_20100106 | Correspondence | Independent Electricity System Operator - IESO | 2010-01-06 | 2010-01-06 | |
EB-2009-0377 | po1_IESO fees 2010_20091223 | Procedural Order | Independent Electricity System Operator - IESO | 2009-12-23 | 2009-12-23 | |
EB-2009-0377 | Intervention list_IESO_20091223 | Intervenor List | Independent Electricity System Operator - IESO | 2009-12-23 at 10:15 AM | ||
EB-2009-0377 | IESO_LTR_20091217 | Correspondence | Independent Electricity System Operator - IESO | 2009-12-17 | 2009-12-17 | |
EB-2009-0377 | AMPCO_Intervention_REQ_20091209 | Intervenor Request Letter | Independent Electricity System Operator - IESO | 2009-12-10 | 2009-12-10 | |
EB-2009-0377 | VECC_Intervention reply_20091209 | Intervenor Request Objection | Independent Electricity System Operator - IESO | 2009-12-09 | 2009-12-09 | |
EB-2009-0377 | Society_Intervention reply_20091209 | Intervenor Request Objection | Independent Electricity System Operator - IESO | 2009-12-09 | 2009-12-09 | |
EB-2009-0377 | Shell_Intervention reply_20091209 | Intervenor Request Objection | Independent Electricity System Operator - IESO | 2009-12-09 | 2009-12-09 | |
EB-2009-0377 | OPG_Intervention reply_20091209 | Intervenor Request Letter | Independent Electricity System Operator - IESO | 2009-12-09 | 2009-12-09 | |
EB-2009-0377 | OPA_Intervention reply_20091209 | Intervenor Request Letter | Independent Electricity System Operator - IESO | 2009-12-09 | 2009-12-09 | |
EB-2009-0377 | EP_Intervention reply_20091209 | Intervenor Request Letter | Independent Electricity System Operator - IESO | 2009-12-09 | 2009-12-09 | |
EB-2009-0377 | VECC_Intervention reply_20091209 | Intervenor Request Objection | Independent Electricity System Operator - IESO | 2009-12-09 | 2009-12-09 | |
EB-2009-0377 | EP_IntvRQST_20091208 | Intervenor Request Letter | Independent Electricity System Operator - IESO | 2009-12-08 | 2009-12-08 | |
EB-2009-0377 | VECC_INTERVENTION_20091203 | Intervenor Request Letter | Independent Electricity System Operator - IESO | 2009-12-03 | 2009-12-03 | |
EB-2009-0377 | ShellEnergy_Intervention_REQ_20091202 | Intervenor Request Letter | Independent Electricity System Operator - IESO | 2009-12-02 | 2009-12-02 | |
EB-2009-0377 | OPG_IESO_Intv_REQ_20091201 | Intervenor Request Letter | Independent Electricity System Operator - IESO | 2009-12-01 | 2009-12-01 | |
EB-2009-0377 | OPA_IntvRQST_IESO_20091201 | Intervenor Request Letter | Independent Electricity System Operator - IESO | 2009-11-30 | 2009-11-30 | |
EB-2009-0377 | Society_InterventionRequest_IESO_20091127 | Intervenor Request Letter | Independent Electricity System Operator - IESO | 2009-11-27 | 2009-11-27 | |
EB-2009-0377 | NOA_IESO_20010Fees_ENG_20091125 | Notice of Application and Notice of Hearing | Independent Electricity System Operator - IESO | 2009-11-25 | 2009-11-25 | |
EB-2009-0377 | NOA_IESO_20010Fees_20091125_FR | Notice of Application and Notice of Hearing | Independent Electricity System Operator - IESO | 2009-11-25 | 2009-11-25 | |
EB-2009-0377 | NOA_IESO_20010Fees_ENG_20091125 | Notice of Application and Notice of Hearing | Independent Electricity System Operator - IESO | 2009-11-25 | 2009-11-25 | |
EB-2009-0377 | IESO_2010 Fees Submission Application_20091102 | Application and Evidence | Independent Electricity System Operator - IESO | 2009-11-03 | 2009-11-03 | |
EB-2009-0377 | Ack_ltr_IESO_20091110 | Acknowledgement Letter | Independent Electricity System Operator - IESO | 2009-11-10 | 2009-11-10 | |
Case Number | File Name | Document Type | Applicant | Issued By OEB | Received By OEB | Date Issued/Received |