EB-2019-0037
|
Final Rate Order_Greater Sudbury Hydro_C-19 Forgone Rev_20201008
|
Rate Order
|
2020-10-08
|
|
2020-10-08
|
EB-2019-0037
|
GSHi_LTR_Rate_Implementation_and_Forgone_Revenue_Follow_Up_20200921
|
Correspondence
|
|
2020-09-21
|
2020-09-21
|
EB-2019-0037
|
GSHi_COVID19_Forgone_Rev_Rate_Rider_Model_20200921
|
Correspondence
|
|
2020-09-21
|
2020-09-21
|
EB-2019-0037
|
GSHi_LTR_Rate_Implementation_and_Forgone_Revenue_20200915
|
Correspondence
|
|
2020-09-15
|
2020-09-15
|
EB-2019-0037
|
Dec_Order_on Cost Awards_GSHI_20200622
|
Decision and Order on Cost Awards
|
2020-06-22
|
|
2020-06-22
|
EB-2019-0037
|
SEC_cost claim_Signed Affidavit_20200610
|
Cost Claim
|
|
2020-06-10
|
2020-06-10
|
EB-2019-0037
|
PollutionProbe_CostClaim_20200520
|
Cost Claim
|
|
2020-05-20
|
2020-05-20
|
EB-2019-0037
|
SEC_CostClaim_GSHI_20200520
|
Cost Claim
|
|
2020-05-20
|
2020-05-20
|
EB-2019-0037
|
VECC_Cost Claim_ 20200519
|
Cost Claim
|
|
2020-05-19
|
2020-05-19
|
EB-2019-0037
|
EP_Cost Claim_20200514
|
Cost Claim
|
|
2020-05-14
|
2020-05-14
|
EB-2019-0037
|
dec_order_Greater Sudbury-20200507
|
Rate Order
|
2020-05-07
|
|
2020-05-07
|
EB-2019-0037
|
dec_order_Greater Sudbury-20200507
|
Decision
|
2020-05-07
|
|
2020-05-07
|
EB-2019-0037
|
Interim Rate Order_GSHI_20200430
|
Interim order
|
2020-04-30
|
|
2020-04-30
|
EB-2019-0037
|
PollutionProbe_Ltr_20200429
|
Correspondence
|
|
2020-04-29
|
2020-04-29
|
EB-2019-0037
|
OEB_Ltr_Settlement Proposal_GSHI_20200427
|
Correspondence
|
2020-04-28
|
|
2020-04-28
|
EB-2019-0037
|
Sudbury Hydro settlement staff sub_20200424
|
Submission
|
|
2020-04-24
|
2020-04-24
|
EB-2019-0037
|
GSHI_CORRESPONDENCE_Implementation_Delay_20200423
|
Correspondence
|
|
2020-04-23
|
2020-04-23
|
EB-2019-0037
|
GSHI_SETTLEMENT_2020_Test_year_Income_Tax_PILs_20200420
|
Settlement Proposal
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_SETTLEMENT_2020_Tariff_Schedule_and_Bill_Impact_Model_20200420
|
Settlement Proposal
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_SETTLEMENT_2020_RTSR_Workform_20200420
|
Settlement Proposal
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_SETTLEMENT_2020_Rev_Reqt_Work_Form_20200420
|
Settlement Proposal
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_SETTLEMENT_2020_LRAMVA_Workform_20200420
|
Settlement Proposal
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_SETTLEMENT_2020_Load_Forecast_20200420
|
Settlement Proposal
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_SETTLEMENT_2020_Final_Tariffs_20200420
|
Settlement Proposal
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_SETTLEMENT_2020_Filing_Requirements_Chapter_2_Appendices_20200420
|
Settlement Proposal
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_SETTLEMENT_2020_DVA_Continuity_Schedule_CoS_20200420
|
Settlement Proposal
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_SETTLEMENT_2020_Cost_Allocation_Model_v3.7_20200420
|
Settlement Proposal
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_SETTLEMENT_2020_CoP_combined_20200420
|
Settlement Proposal
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_SETTLEMENT_2020_ACM_ICM_Model_20200420
|
Settlement Proposal
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_SETTLEMENT_Proposal_20200420
|
Settlement Proposal
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_SETTLEMENT_Cover_Letter_20200420
|
Settlement Proposal
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_Pre-ADR_VECC_56_2020_Rev_Reqt_Work_Form_Interrogatories_Revised_2021_22_RC_Ratios_And_GSgt50_
|
Interrogatory Response from Applicant
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_Pre_ADR_VECC_55_GSHI_IRR_2020_Tariff_Schedule_and_Bill_Impact_Model_20200421
|
Interrogatory Response from Applicant
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_Pre_ADR_VECC_55_GSHI_IRR_2020_Cost_Allocation_Model_v3.7_20200421
|
Interrogatory Response from Applicant
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_Pre_ADR_VECC_55_GSH_2020_Load_Forecast_20200421
|
Interrogatory Response from Applicant
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_Pre_ADR_Staff_98_GSHI_Pre_Settlement_2019_RPP_NonRPP_Data_20200421
|
Interrogatory Response from Applicant
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_Pre_ADR_Staff_97_GSHI_IRR_2020-ACM_ICM_Model_20200421
|
Interrogatory Response from Applicant
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
GSHI_Pre-ADR_Response_to_Pre_Settlement_Clarification_Questions_20200421
|
Interrogatory Response from Applicant
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
OEB_Ltr_Granting_Ext_GSHI_20200420
|
Correspondence
|
2020-04-20
|
|
2020-04-20
|
EB-2019-0037
|
GSHI_SETTLEMENT_Delay_20200417
|
Correspondence
|
|
2020-04-20
|
2020-04-20
|
EB-2019-0037
|
dec_Issues List_GSHI_20200318
|
Decision
|
2020-03-18
|
|
2020-03-18
|
EB-2019-0037
|
GSHI_IRR_SEC_16_20200317
|
Interrogatory Response from Applicant
|
|
2020-03-17
|
2020-03-17
|
EB-2019-0037
|
GSHI_IRR_Participation_and_Cost_Report_GSH_20200317
|
Interrogatory Response from Applicant
|
|
2020-03-17
|
2020-03-17
|
EB-2019-0037
|
GSHI_IRR_Response_Cover_Letter_20200317
|
Interrogatory Response from Applicant
|
|
2020-03-17
|
2020-03-17
|
EB-2019-0037
|
Proposed Issues List_Sudbury Hydro_20200316
|
Correspondence
|
|
2020-03-16
|
2020-03-16
|
EB-2019-0037
|
GSHI_IRR_Update_of_Demand_Data_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_SG_Revenue_Requirement_Calc_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_SEC_13_Updated_Table_11_from_DSP_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_LETTER_OF_COMMENT_RESPONSE_NYKILCHUK_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_LETTER_OF_COMMENT_RESPONSE_MUZYKA_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_Cost_of_Power_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_Attachment_3_Staff_40_b_i_Post_Term_Projects
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2020_Test_Year_Income_Tax_PILs_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2020_Tariff_Schedule_and_Bill_Impact_Model_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2020_RTSR_Workform_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2020_Rev_Reqt_Work_Form_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2020_LRAMVA_Workform_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2020_Load_Forecast_Model_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2020_GA_Analysis_Workform_v1.9_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2020_Filing_Requirements_Chapter2_Appendices_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2020_EP_22_Comparative_Appendix_2K_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2020_DVA_Continuity_Schedule_CoS_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2020_Cost_Allocation_Model_v3.7_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2020_ACM_ICM_Model_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2018_Participation_and_Cost_Report_Greater_Sudbury_Hydro_Inc_2019_ 01_2
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2017_Final_Verified_Annual_Program_Results_Greater_Sudbury_Hydro
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2016_Final_Verified_Annual_LDC_CDM_Program_Results_Report_Greater_Sudbur
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2015_Final_Annual_Verified_Results_Report_Annual_Persistence_Greater S
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2011-2014_Persistence_Report_Greater_Sudbury_Hydro_Inc._v2
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_2006-2010_Final_OPA_CDM_Results_Greater_Sudbury_Hydro_Inc
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_Pollution_Probe_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_School_Energy_Coalition_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_Vulnerable_Energy_Consumers_Coalition_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_Energy_Probe_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_Response_Cover_Letter_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
GSHI_IRR_Board_Staff_20200310
|
Interrogatory Response from Applicant
|
|
2020-03-10
|
2020-03-10
|
EB-2019-0037
|
po2_GHSI_20190302
|
Procedural Order
|
2020-03-02
|
|
2020-03-02
|
EB-2019-0037
|
GSHI_filing extension request_IRR_20200227
|
Correspondence
|
|
2020-02-27
|
2020-02-27
|
EB-2019-0037
|
SEC_IRS_GHSI_2020212
|
Interrogatories to Applicant
|
|
2020-02-12
|
2020-02-12
|
EB-2019-0037
|
PollutionProbe_IRs_GSHI_20200212
|
Interrogatories to Applicant
|
|
2020-02-12
|
2020-02-12
|
EB-2019-0037
|
Energy Probe _IRS_to GSHI 2020_20200211
|
Interrogatories to Applicant
|
|
2020-02-10
|
2020-02-10
|
EB-2019-0037
|
OEB IRs_Sudbury Hydro_20200207
|
Interrogatories to Applicant
|
|
2020-02-07
|
2020-02-07
|
EB-2019-0037
|
OEB IR_2021 CoP_combined_20191111_20200207
|
Interrogatories to Applicant
|
|
2020-02-07
|
2020-02-07
|
EB-2019-0037
|
PO 1_GSHI_20200122
|
Procedural Order
|
2020-01-22
|
|
2020-01-22
|
EB-2019-0037
|
GSHI_APPL_Intervenors_20200121.pdf
|
Correspondence
|
|
2020-01-21
|
2020-01-21
|
EB-2019-0037
|
PollutionProbe_IntrvREQ_GSHI_20200117
|
Intervenor Request Letter
|
|
2020-01-17
|
2020-01-17
|
EB-2019-0037
|
EnergyProbe_IntrvREQ_GSHI_20191225
|
Intervenor Request Letter
|
|
2019-12-25
|
2019-12-25
|
EB-2019-0037
|
Musyka_ltr of Comments_20191223_Redacted
|
Letter of Comment
|
|
2019-12-23
|
2019-12-23
|
EB-2019-0037
|
Nykilchuk_ltr of Comments_20191223_Redacted
|
Letter of Comment
|
|
2019-12-23
|
2019-12-23
|
EB-2019-0037
|
VECC_intvRQST_Sudbury Hydro.pdf
|
Intervenor Request Letter
|
|
2019-12-20
|
2019-12-20
|
EB-2019-0037
|
SEC_IntvRqst_20191219
|
Intervenor Request Letter
|
|
2019-12-19
|
2019-12-19
|
EB-2019-0037
|
GSHI_Notice_Signed_Affidavit_20191219
|
Affidavits of Service
|
|
2019-12-19
|
2019-12-19
|
EB-2019-0037
|
GSHI_APPL_Corrected_Customer_Summary_20191219
|
Application and Evidence
|
|
2019-12-19
|
2019-12-19
|
EB-2019-0037
|
GSHI_APPL_Corrected_Customer_Summary_Cvrltr_20191219
|
Application and Evidence
|
|
2019-12-19
|
2019-12-19
|
EB-2019-0037
|
Notice_GSHI_Fr_20191216
|
Notice
|
2019-12-16
|
|
2019-12-16
|
EB-2019-0037
|
Notice_GSHI_En_20191216
|
Notice
|
2019-12-16
|
|
2019-12-16
|
EB-2019-0037
|
lod_GSHI_2020 CoS_20191216
|
Letter of Direction
|
2019-12-16
|
|
2019-12-16
|
EB-2019-0037
|
OEBltr_Appl Complete_GSHI_20191202
|
Correspondence
|
2019-12-02
|
|
2019-12-02
|
EB-2019-0037
|
GSHI_2020_Filing_Requirements_Chapter2_Appendices_20191126
|
Application and Evidence
|
|
2019-11-25
|
2019-11-25
|
EB-2019-0037
|
GSHI_Response_to_Incomplete_20191126
|
Correspondence
|
|
2019-11-26
|
2019-11-26
|
EB-2019-0037
|
GSHI_APPL_2020_Filing_Requirements_Chapter2_Appendices_20191115
|
Correspondence
|
2019-11-15
|
|
2019-11-15
|
EB-2019-0037
|
OEB_Incomplete Ltr_to Greater Sudbury_20191115
|
Correspondence
|
2019-11-15
|
|
2019-11-15
|
EB-2019-0037
|
Ack_Letter_GSHI_20191104
|
Acknowledgement Letter
|
2019-11-04
|
|
2019-11-04
|
EB-2019-0037
|
GSHI_APPL_2020_Load_Forecast_Model_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_Update_of_Demand_Data_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHi_APPL_2020_ACM_ICM_Model_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_1595_Analysis_Workform_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Filing_Requirements_Chapter2_Appendices_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Benchmarking_Spreadsheet_Forecast_Model_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_RTSR_Workform_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_LRAMVA_Workform_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Test_Year_Income_Tax_PILs_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Proposed_Tariffs_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_DVA_Continuity_Schedule_CoS_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Tariff_Schedule_and_Bill_Impact_Model_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Filing_Requirements_Chapter_5_Appendix_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Rev_Reqt_Work_Form_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Cost_Allocation_Model_v3.7_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_GA_Analysis_Workform_v1.9_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Checklist_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHi_APPL_2020_ACM_ICM_Model_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_1595_Analysis_Workform_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Filing_Requirements_Chapter2_Appendices_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Benchmarking_Spreadsheet_Forecast_Model_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_RTSR_Workform_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Test_Year_Income_Tax_PILs_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_LRAMVA_Workform_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Proposed_Tariffs_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_DVA_Continuity_Schedule_CoS_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Tariff_Schedule_and_Bill_Impact_Model_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Filing_Requirements_Chapter_5_Appendix_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Rev_Reqt_Work_Form_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Cost_Allocation_Model_v3.7_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_GA_Analysis_Workform_v1.9_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_2020_Checklist_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_Customer_Summary_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_Exhibit_9_Deferral_and_Variance_Accounts_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_Exhibit_8_Rate_Design_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_Exhibit_7_Cost_Allocation_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_Exhibit_6_Revenue_Deficiency_or_Sufficiency_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_Exhibit_5_Cost_of_Capital_and_Rate_of_Return_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_Exhibit_4_Operating_Costs_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_Exhibit_3_Operating_Revenue_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_Exhibit_2_Rate_Base_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_Exhibit_1_Administrative_Documents_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
GSHI_APPL_Cover_Letter_COS_Application_20191031
|
Application and Evidence
|
|
2019-10-31
|
2019-10-31
|
EB-2019-0037
|
OEB_ltr_Greater Sudbury_20190725
|
Correspondence
|
2019-07-25
|
|
2019-07-25
|
EB-2019-0037
|
GSHI_Letter_Delay_Filing_20190724
|
Correspondence
|
|
2019-07-23
|
2019-07-23
|