Case Number File Name Document Type Applicant Issued By OEB Received By OEB Date Issued/Received
EB-2023-0071 document icon OEB_ltr_EVC Rate Announcement_20250918_esigned Correspondence Ontario Energy Board 2025-09-18 2025-09-18
EB-2023-0071 document icon dec_order_cost_awards_EV Integration_20250728_esigned Decision and Order on Cost Awards Ontario Energy Board 2025-07-28 2025-07-28
EB-2023-0071 document icon PollutionProbe_EVI_Cost Claim Addendum_20250714 Cost Claim Ontario Energy Board 2025-07-12 2025-07-12
EB-2023-0071 document icon BOMA_Cost Claim_EVI_20250618 Cost Claim Ontario Energy Board 2025-06-18 2025-06-18
EB-2023-0071 document icon DRC_Cost Claim_EVI_20250618 Cost Claim Ontario Energy Board 2025-06-18 2025-06-18
EB-2023-0071 document icon VECC_Cost Claim_EVI_20250617 Cost Claim Ontario Energy Board 2025-06-18 2025-06-18
EB-2023-0071 document icon ED_Cost Claim_EVI_20250617 Cost Claim Ontario Energy Board 2025-06-17 2025-06-17
EB-2023-0071 document icon SEC_Cost Claim_EVI_20250616 Cost Claim Ontario Energy Board 2025-06-16 2025-06-16
EB-2023-0071 document icon CCMBC_Cost Claim_EVI_20250604 Cost Claim Ontario Energy Board 2025-06-04 2025-06-04
EB-2023-0071 document icon PollutionProbe_Cost Claim_EVI_20250603 Cost Claim Ontario Energy Board 2025-06-03 2025-06-03
EB-2023-0071 document icon NoH_Cost Awards_Electric Vehicle Integration_20250528 Notice of Hearing for Cost Awards Ontario Energy Board 2025-05-28 2025-05-28
EB-2023-0071 document icon Accounting Order_EVC Rates_20250430_esigned Rate Order Ontario Energy Board 2025-04-30 2025-04-30
EB-2023-0071 document icon EVC Rate Frequently Asked Questions_20250331 Correspondence Ontario Energy Board 2025-03-31 2025-03-31
EB-2023-0071 document icon EVC Rate Overview Report March 2025 Final update blackline_20250331 Report of the OEB Ontario Energy Board 2025-03-31 2025-03-31
EB-2023-0071 document icon EVC Rate Overview Report March 2025 Final update_clean_20250331 Report of the OEB Ontario Energy Board 2025-03-31 2025-03-31
EB-2023-0071 document icon OEBltr_EVC Rate Announcement_20250331_eSigned Correspondence Ontario Energy Board 2025-03-31 2025-03-31
EB-2023-0071 document icon DRC_Addl Counsel_DeMarco_D Vollmer_EVC Charging Consultation_20250307 Correspondence Ontario Energy Board 2025-03-07 2025-03-07
EB-2023-0071 document icon THESL_EVRateDesign_Comments_20250206 Comments Ontario Energy Board 2025-02-06 2025-02-06
EB-2023-0071 document icon EDA_Revised Proposal_EV Charging_20250205 Comments Ontario Energy Board 2025-02-05 2025-02-05
EB-2023-0071 document icon VECC_Comments_Delivery Rates for EV chanrging_20250203 Comments Ontario Energy Board 2025-02-03 2025-02-03
EB-2023-0071 document icon BOMA_comments_Public_EVC_rates_20250103 Comments Ontario Energy Board 2025-01-31 2025-01-31
EB-2023-0071 document icon HOL_Comments_EVC Rate Rule Proposal_20250203 Comments Ontario Energy Board 2025-01-31 2025-01-31
EB-2023-0071 document icon HONI_Comments_EVC Rate_20250131 Comments Ontario Energy Board 2025-01-31 2025-01-31
EB-2023-0071 document icon ED_Comments_EV Charging Rates_20250131 Comments Ontario Energy Board 2025-01-31 2025-01-31
EB-2023-0071 document icon PollutionProbe_Comments_EVIntegration_20250131 Comments Ontario Energy Board 2025-01-31 2025-01-31
EB-2023-0071 document icon DRC_Comments_EVI Final_20250131 Comments Ontario Energy Board 2025-01-31 2025-01-31
EB-2023-0071 document icon SWTCH-ChargePoint-Tesla-FLO Revised EVC Rate Submission_20250129 Correspondence Ontario Energy Board 2025-01-29 2025-01-29
EB-2023-0071 document icon OEBltr_EVC Rate Announcement_Notice of Cost Awards Process_20250107_esigned Correspondence; Notice Ontario Energy Board 2025-01-07 2025-01-07
EB-2023-0071 document icon Consultant Memo_EV Delivery Rate_Impact of Venue_20241015 Report of the OEB Ontario Energy Board 2025-01-07 2025-01-07
EB-2023-0071 document icon EVC Rate_Companion Report_20250107 Report of the OEB Ontario Energy Board 2025-01-07 2025-01-07
EB-2023-0071 document icon EVC_Rate Overview Report_20250107 Report of the OEB Ontario Energy Board 2025-01-07 2025-01-07
EB-2023-0071 document icon Baseload Power Corp_LOC_Electricity Delivery Rates for EV Charging_20240702 Letter of Comment Ontario Energy Board 2024-06-28 2024-06-28
EB-2023-0071 document icon ChargePoint_Comments Electric Vehicle Integration (EVI) Initiative_20240628 Comments Ontario Energy Board 2024-06-28 2024-06-28
EB-2023-0071 document icon EVC_EDA_Comments_20240628 Comments Ontario Energy Board 2024-06-27 2024-06-27
EB-2023-0071 document icon BOMA_comments_Public_EVC_rates_20240627 Comments Ontario Energy Board 2024-06-27 2024-06-27
EB-2023-0071 document icon Tesla Motors Canada_Comments_EVI Charging_20240627 Comments Ontario Energy Board 2024-06-27 2024-06-27
EB-2023-0071 document icon FLO_Comments_EVI Delivery Rates_20240627 Comments Ontario Energy Board 2024-06-27 2024-06-27
EB-2023-0071 document icon Hydro Ottawa_Comments_EVI_20240627 Comments Ontario Energy Board 2024-06-27 2024-06-27
EB-2023-0071 document icon DRC_Comments_EVI_20240627 Comments Ontario Energy Board 2024-06-27 2024-06-27
EB-2023-0071 document icon CCMBC_Comments_EVI_20240627 Comments Ontario Energy Board 2024-06-27 2024-06-27
EB-2023-0071 document icon HONI_EVI_Comments_20240627 Comments Ontario Energy Board 2024-06-27 2024-06-27
EB-2023-0071 document icon VECC_Comments_EVI_20240627 Comments Ontario Energy Board 2024-06-27 2024-06-27
EB-2023-0071 document icon SEC_Comments_EVI_20240626 Comments Ontario Energy Board 2024-06-26 2024-06-26
EB-2023-0071 document icon EVC Rate_Presentation QA_20240619 Correspondence Ontario Energy Board 2024-06-21 2024-06-21
EB-2023-0071 document icon SWTCH_Comments_EVI_20240620 Comments Ontario Energy Board 2024-06-20 2024-06-20
EB-2023-0071 document icon PollutionProbe_Comments_EV Integration_20240620 Comments Ontario Energy Board 2024-06-20 2024-06-20
EB-2023-0071 document icon OEBltr_Delivery Costs_EVI Stakeholder Meeting Material_20240530_esigned Correspondence Ontario Energy Board 2024-05-30 2024-05-30
EB-2023-0071 document icon Dec_Cost Eligiblity_EVI Integration Stakeholder Meeting_20240530_esigned Cost Eligibility Decision Ontario Energy Board 2024-05-30 2024-05-30
EB-2023-0071 document icon POWER ADVISORY_EVI Delivery Costs_Stakeholder Presentation_20240530 Correspondence Ontario Energy Board 2024-05-30 2024-05-30
EB-2023-0071 document icon OEB_Electricity Delivery Rates_EV Charging_Presentation_20240530 Correspondence Ontario Energy Board 2024-05-30 2024-05-30
EB-2023-0071 document icon OEB Staff Discussion Paper_EVI Stakehlolder Meeting_20240530 Correspondence Ontario Energy Board 2024-05-30 2024-05-30
EB-2023-0071 document icon Power Advisory Addendum 1_Analysis and Rate Design Report_20240529 Report of the OEB Ontario Energy Board 2024-05-29 at 11:07 AM
EB-2023-0071 document icon Power Advisory Addendum 2_Implementation Considerations Report_20240529 Report of the OEB Ontario Energy Board 2024-05-29 at 11:08 AM
EB-2023-0071 document icon DRC_PartREQ_EVI Delivery Costs_20240522 Participation Request Letter Ontario Energy Board 2024-05-22 2024-05-22
EB-2023-0071 document icon Ivy Charge_Req for Participation_EVI Integration_20240510 Participation Request Letter Ontario Energy Board 2024-05-10 2024-05-10
EB-2023-0071 document icon SEC_PartREQ_EVI Stakeholder Meeting_20240503 Participation Request Letter Ontario Energy Board 2024-05-02 2024-05-02
EB-2023-0071 document icon OEBltr_Stakeholder Meeting_EVI_Delivery Costs_20240501_esigned Correspondence Ontario Energy Board 2024-05-01 2024-05-01
EB-2023-0071 document icon dec_order_cost awards_EV Rates Integration_20240318 Decision and Order on Cost Awards Ontario Energy Board 2024-03-18 2024-03-18
EB-2023-0071 document icon CCC_Cost Claim-EVI Initiative_20240131 Cost Claim Ontario Energy Board 2024-01-31 2024-01-31
EB-2023-0071 document icon CCMBC_Cost Claim_EVI Initiative_20240126 Cost Claim Ontario Energy Board 2024-01-26 2024-01-26
EB-2023-0071 document icon P_PRO_Cost Claim_EVI Initiative_20240126 Cost Claim Ontario Energy Board 2024-01-26 2024-01-26
EB-2023-0071 document icon ED_Cost Claim_EVI Initiative_20240125 Cost Claim Ontario Energy Board 2024-01-25 2024-01-25
EB-2023-0071 document icon VECC_Cost Claim_EV Initiative_20240125 Cost Claim Ontario Energy Board 2024-01-25 2024-01-25
EB-2023-0071 document icon NOH_Cost Awards_Electric Vehicle Integration_20240118 Notice of Hearing for Cost Awards Ontario Energy Board 2024-01-18 2024-01-18
EB-2023-0071 document icon OEBLtr_System Investments for EV Integration_20230828 Correspondence Ontario Energy Board 2023-08-28 2023-08-28
EB-2023-0071 document icon TTC_Comments_EVI Initiative_20230615_Redacted Comments Ontario Energy Board 2023-06-15 2023-06-15
EB-2023-0071 document icon IESO_Comments_EVI Initiative_20230614 Comments Ontario Energy Board 2023-06-14 2023-06-14
EB-2023-0071 document icon ED_Comments_EVI Initiative_20230614 Comments Ontario Energy Board 2023-06-15 2023-06-15
EB-2023-0071 document icon CCC_Comments_EVI Initiative_20230614 Comments Ontario Energy Board 2023-06-14 2023-06-14
EB-2023-0071 document icon ChargePointFLOTeslaSuncorEnel_Comment_EVI Initiative_20230614 Comments Ontario Energy Board 2023-06-14 2023-06-14
EB-2023-0071 document icon TAF_Comments_EVI Initiative_20230614 Comments Ontario Energy Board 2023-06-14 2023-06-14
EB-2023-0071 document icon CCMBC_Comments_EVI Initiative_20230614 Comments Ontario Energy Board 2023-06-14 2023-06-14
EB-2023-0071 document icon CLD_Comments_EVI Initiative_20230614 Comments Ontario Energy Board 2023-06-14 2023-06-14
EB-2023-0071 document icon EDA_Comments_EVI Initiative_20230614 Comments Ontario Energy Board 2023-06-14 2023-06-14
EB-2023-0071 document icon HONI_Comments_EVI Initiative_20230614 Comments Ontario Energy Board 2023-06-14 2023-06-14
EB-2023-0071 document icon FreeWire Technologies_Comment_EVI Initiative_20230614 Comments Ontario Energy Board 2023-06-14 2023-06-14
EB-2023-0071 document icon Baseload Power_Comments_EV Integration Initiative_20230614 Comments Ontario Energy Board 2023-06-14 2023-06-14
EB-2023-0071 document icon Energy Storage_Comments_EVI Initiative_20230613 Comments Ontario Energy Board 2023-06-14 2023-06-14
EB-2023-0071 document icon PollutionPorbe_Comments_EVI Integration Initiative_20230614 Comments Ontario Energy Board 2023-06-13 2023-06-13
EB-2023-0071 document icon VECC_Comments_EVI Initiative_20230613 Comments Ontario Energy Board 2023-06-13 2023-06-13
EB-2023-0071 document icon OEBltr_EVI Feedback Extension_20230531 Correspondence Ontario Energy Board 2023-05-31 2023-05-31
EB-2023-0071 document icon OEB_EV Delivery Rates Report_May 24 2023 Stakeholder Meeting_20230517 Correspondence Ontario Energy Board 2023-05-17 2023-05-17
EB-2023-0071 document icon POWER ADVISORY_EVI Delivery Costs_Stakeholder Presentation_20230517 Correspondence Ontario Energy Board 2023-05-17 2023-05-17
EB-2023-0071 document icon Dec_ on Cost Eligiblity_20230505 Cost Eligibility Decision Ontario Energy Board 2023-05-05 2023-05-05
EB-2023-0071 document icon BOMA_PartREQ_20230427 Intervenor Request Letter; Participation Request Letter Ontario Energy Board 2023-04-27 2023-04-27
EB-2023-0071 document icon VECC_PartiREQ_20230427 Participation Request Letter Ontario Energy Board 2023-04-27 2023-04-27
EB-2023-0071 document icon CCMBC_PartREQ_20230424.pdf Participation Request Letter Ontario Energy Board 2023-04-24 2023-04-24
EB-2023-0071 document icon CCC_PartRQST_OEB.Consultation.ElectricVehicle_20230424 Participation Request Letter Ontario Energy Board 2023-04-24 2023-04-24
EB-2023-0071 document icon Pollution Probe_2023_PartRQST_Annual_Filing_20230424 Participation Request Letter Ontario Energy Board 2023-04-24 2023-04-24
EB-2023-0071 document icon Pollution Probe_ZParRQST_20230424 Participation Request Letter Ontario Energy Board 2023-04-24 2023-04-24
EB-2023-0071 document icon ED_PartReq_20230419 Participation Request Letter Ontario Energy Board 2023-04-19 2023-04-19
EB-2023-0071 document icon OEB_2023 EV Rates Report_20230413 Correspondence Ontario Energy Board 2023-04-13 2023-04-13
EB-2023-0071 document icon OEBltr_EVI meeting Invitation_Notice of Cost Awards Process_20230413 Correspondence Ontario Energy Board 2023-04-13 2023-04-13
EB-2023-0071 document icon OEBltr_EV Survey_Consultant Report_20230201 Correspondence Ontario Energy Board 2023-02-01 2023-02-01
EB-2023-0071 document icon EVI_Consultant Report_EV Survey Results_20230127 Correspondence Ontario Energy Board 2023-02-01 2023-02-01