Search Results for: Records - Case Number=EB-2020-0042 - 40 Records Found
The document result list has reached its limit of 10,000 records. Please refine your search criteria to view more records.
Sorting Your Search Results
The most recent documents automatically show at the top. To sort by different categories (e.g. by Document Type) click the column header. Click it again to switch between ascending/descending order.
Case Information
Click the case number to view details for that proceeding.
Case Number | File Name | Document Type | Applicant | Issued By OEB | Received By OEB | Date Issued/Received |
---|---|---|---|---|---|---|
EB-2020-0042 | dec_order_cost awards_NOTL_20210421 | Decision and Order on Cost Awards | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-04-21 | 2021-04-21 | |
EB-2020-0042 | NOTLH 2021-IRM-Rate-Generator-Model_20210405 | Rate Model | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-04-05 | 2021-04-05 | 2021-04-05 |
EB-2020-0042 | OEB_ltr_NOTL_IRM_20210405 | Correspondence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-04-05 | 2021-04-05 | |
EB-2020-0042 | VECC_Cost Claim_20210331 | Cost Claim | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-03-31 | 2021-03-31 | |
EB-2020-0042 | NOTL_response_Decision and Rate Order_20210326 | Correspondence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-03-26 | 2021-03-26 | |
EB-2020-0042 | dec_rate_order_NOTLH_2021_Generic_LRAMVA_Workform to April 30 2019_20210325 | Rate Model | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-03-25 | 2021-03-25 | |
EB-2020-0042 | dec_rate_order_NOTLH_2021_Generic_LRAMVA_Workform- May 1-Dec 31 2019_20210325 | Rate Model | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-03-25 | 2021-03-25 | |
EB-2020-0042 | dec_rate_order_NOTLH 2021-IRM-Rate-Generator-Model_20210325 | Rate Model | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-03-25 | 2021-03-25 | |
EB-2020-0042 | dec_rate_order_Niagara on the lake_2021 IRM_20210325 | Rate Order | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-03-25 | 2021-03-25 | |
EB-2020-0042 | dec_rate_order_Niagara on the lake_2021 IRM_20210325 | Decision | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-03-25 | 2021-03-25 | |
EB-2020-0042 | NOTL Hydro_sub_20210204 | Submission | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-02-05 | 2021-02-05 | |
EB-2020-0042 | VECC_SUB_NOTL_20210201 | Submission | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-02-02 | 2021-02-02 | |
EB-2020-0042 | OEB Staff_Submission_NOTL_20210201 | Submission | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-02-01 | 2021-02-01 | |
EB-2020-0042 | NOTL_IRR_Hydro Letter_IPI_20210121 | Interrogatory Response from Applicant | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-01-21 | 2021-01-21 | |
EB-2020-0042 | NOTL_IRR_VECC_20210118 | Interrogatory Response from Applicant | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-01-18 | 2021-01-18 | |
EB-2020-0042 | NOTLH_2021-IRM-Rate-Generator-Model_V2_20210118 | Interrogatory Response from Applicant | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-01-18 | 2021-01-18 | |
EB-2020-0042 | NOTLH_2021_Generic_LRAMVA_Workform to April 30, 2019_20210118 | Interrogatory Response from Applicant | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-01-18 | 2021-01-18 | |
EB-2020-0042 | NOTLH_2021_Generic_LRAMVA_Workform- May 1-Dec 31, 2019_20210118 | Interrogatory Response from Applicant | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-01-18 | 2021-01-18 | |
EB-2020-0042 | NOTL_IRR_OEB_20210118 | Interrogatory Response from Applicant | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-01-18 | 2021-01-18 | |
EB-2020-0042 | VECC_IR_NOTL_20210104 | Interrogatories to Applicant | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-01-04 | 2021-01-04 | |
EB-2020-0042 | VECC_IR_cvrltr_NOTL_20210104 | Interrogatories to Applicant | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-01-04 | 2021-01-04 | |
EB-2020-0042 | OEBstaff_IR_Niagara on the Lake_2021 IRM_20210104 | Interrogatories to Applicant | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2021-01-04 | 2021-01-04 | |
EB-2020-0042 | OEB Reply_VECC Late IntrvREQ_NOTL_20201214 | Correspondence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-12-14 | 2020-12-14 | |
EB-2020-0042 | VECC_Response Letter_NOTL_20201204 | Correspondence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-12-04 | 2020-12-04 | |
EB-2020-0042 | NOTL Hydro letter_20201203 | Correspondence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-12-03 | 2020-12-03 | |
EB-2020-0042 | NOTL Hydro_letter_VECC_20201203 | Correspondence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-12-03 | 2020-12-03 | |
EB-2020-0042 | VECC_late_IntrvREQ_NOTL_20121202.pdf | Intervenor Request Letter | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-12-03 | 2020-12-03 | |
EB-2020-0042 | po1_NOTL_20201112 | Procedural Order | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-11-12 | 2020-11-12 | |
EB-2020-0042 | NOTL_Affidavit_20201027 | Affidavits of Service | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-10-27 | 2020-10-27 | |
EB-2020-0042 | noa_NOTL_20202023 | Notice | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-10-23 | 2020-10-23 | |
EB-2020-0042 | lod_NOTL_20201023 | Letter of Direction | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-10-23 | 2020-10-23 | |
EB-2020-0042 | OEB_Complete Letter_NOTL_20201022 | Correspondence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-10-22 | 2020-10-22 | |
EB-2020-0042 | Participation and Cost Report - Niagara-on-the-Lake Hydro Inc. - 2019 04_20201008 | Application and Evidence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-10-08 | 2020-10-08 | |
EB-2020-0042 | 2017 Final Verified Annual LDC CDM Program Results_NOTLH._Report_20180629_20201008 | Application and Evidence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-10-08 | 2020-10-08 | |
EB-2020-0042 | NOTLH - 2021_Generic_LRAMVA_Workform_20201008 | Application and Evidence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-10-08 | 2020-10-08 | |
EB-2020-0042 | NOTLH - 2021_GA_Analysis_Workform_20201008 | Application and Evidence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-10-08 | 2020-10-08 | |
EB-2020-0042 | NOTLH 2021-IRM-Rate-Generator-Model_20201008 | Application and Evidence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-10-08 | 2020-10-08 | |
EB-2020-0042 | NOTLH - 2021_IRM_Checklist_20201008 | Application and Evidence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-10-08 | 2020-10-08 | |
EB-2020-0042 | NOTLH Detail CDM Savings_20201008 | Application and Evidence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-10-08 | 2020-10-08 | |
EB-2020-0042 | NOTL Hydro 2021 IRM Managers Summary_20201008 | Application and Evidence | Niagara-on-the-Lake Hydro Inc. - Electricity Distributor | 2020-10-08 | 2020-10-08 | |
Case Number | File Name | Document Type | Applicant | Issued By OEB | Received By OEB | Date Issued/Received |