Search Results for: Records - Case Number=EB-2022-0325 - 99 Records Found
The document result list has reached its limit of 10,000 records. Please refine your search criteria to view more records.
Sorting Your Search Results
The most recent documents automatically show at the top. To sort by different categories (e.g. by Document Type) click the column header. Click it again to switch between ascending/descending order.
Case Information
Click the case number to view details for that proceeding.
Case Number | File Name | Document Type | Applicant | Issued By OEB | Received By OEB | Date Issued/Received |
---|---|---|---|---|---|---|
EB-2022-0325 | Dec_OEB_UTR_Issue 3 Implementation_20241210_eSigned | Decision | Ontario Energy Board | 2024-12-10 | 2024-12-10 | |
EB-2022-0325 | AMPCO_Reply SUB_UTR_20241101 | Submission | Ontario Energy Board | 2024-11-01 | 2024-11-01 | |
EB-2022-0325 | AMPCO_CVR_LTR_reply submission_20241101 | Submission | Ontario Energy Board | 2024-11-01 | 2024-11-01 | |
EB-2022-0325 | GCC Reply SUB_UTR Ph2_20241030 | Submission | Ontario Energy Board | 2024-10-30 | 2024-10-30 | |
EB-2022-0325 | ED_Reply Sub_UTR Ph2_20241030 | Submission | Ontario Energy Board | 2024-10-30 | 2024-10-30 | |
EB-2022-0325 | VECC Reply SUB_UTR PH2_Issues 4, 5 & 6_20241030 | Submission | Ontario Energy Board | 2024-10-30 | 2024-10-30 | |
EB-2022-0325 | HONI_Reply SUB_UTR_PH 2_Issues 4, 5 and 6_20241030 | Submission | Ontario Energy Board | 2024-10-30 | 2024-10-30 | |
EB-2022-0325 | APPrO_ESC_Reply SUB_UTR Ph2_20241030 | Submission | Ontario Energy Board | 2024-10-30 | 2024-10-30 | |
EB-2022-0325 | LPMA_Reply SUB_UTR PH2_20241030 | Submission | Ontario Energy Board | 2024-10-30 | 2024-10-30 | |
EB-2022-0325 | OEB_Staff_Reply SUB_UTRPh2_20241030_signed | Submission | Ontario Energy Board | 2024-10-30 | 2024-10-30 | |
EB-2022-0325 | LDC Transmission Group_SUB_20241029 | Submission | Ontario Energy Board | 2024-10-29 | 2024-10-29 | |
EB-2022-0325 | APPrO_ESC_SUB_UTR Ph2_20241018 | Submission | Ontario Energy Board | 2024-10-18 | 2024-10-18 | |
EB-2022-0325 | ED_SUB_UTR_20241017 | Submission | Ontario Energy Board | 2024-10-17 | 2024-10-17 | |
EB-2022-0325 | GCC_ SUB_2UTR_0241016 | Submission | Ontario Energy Board | 2024-10-16 | 2024-10-16 | |
EB-2022-0325 | HONI_SUB_ Issues 4, 5 and 6_20241016 | Submission | Ontario Energy Board | 2024-10-16 | 2024-10-16 | |
EB-2022-0325 | SEC_SUB_UTR_20241016 | Submission | Ontario Energy Board | 2024-10-16 | 2024-10-16 | |
EB-2022-0325 | DRC_SUB_UTR_20241016 | Submission | Ontario Energy Board | 2024-10-16 | 2024-10-16 | |
EB-2022-0325 | LPMA_SUB_20241016 | Submission | Ontario Energy Board | 2024-10-16 | 2024-10-16 | |
EB-2022-0325 | VECC_SUB_UTR_Issues 4- 5 & 6_20241016 | Submission | Ontario Energy Board | 2024-10-16 | 2024-10-16 | |
EB-2022-0325 | LDC Transmission Group_SUB_20241016 | Submission | Ontario Energy Board | 2024-10-16 | 2024-10-16 | |
EB-2022-0325 | OEB_Staff_SUB_UTRPh1_20241016_signed | Submission | Ontario Energy Board | 2024-10-16 | 2024-10-16 | |
EB-2022-0325 | GCC_IRR_OEB Staff_UTR PH2_20241008 | Interrogatory Response from Intervenor | Ontario Energy Board | 2024-10-08 | 2024-10-08 | |
EB-2022-0325 | OEBltr_IRR_extension_GCC_20241003_signed | Correspondence | Ontario Energy Board | 2024-10-03 | 2024-10-03 | |
EB-2022-0325 | GWLG Letter re Late Filing of IRRs_20241002 | Interrogatory Response from Intervenor | Ontario Energy Board | 2024-10-02 | 2024-10-02 | |
EB-2022-0325 | Exhibit N1 LDC Transmission Group_IRRs_20241002 | Interrogatory Response from Intervenor | Ontario Energy Board | 2024-10-02 | 2024-10-02 | |
EB-2022-0325 | HONI_IR_EVD_LDCTx_Group_UTR_Phase2_20240912 | Interrogatories to Intervenor | Ontario Energy Board | 2024-09-12 | 2024-09-12 | |
EB-2022-0325 | HONI_IR_EVD_Glencore_UTR_Phase2_20240912 | Interrogatories to Intervenor | Ontario Energy Board | 2024-09-12 | 2024-09-12 | |
EB-2022-0325 | VECC IRs to LDC Transmission Group_UTR_Phase2_20240912 | Interrogatories to Intervenor | Ontario Energy Board | 2024-09-12 | 2024-09-12 | |
EB-2022-0325 | VECC IRs to GCC_UTR_Phase2_20230912 | Interrogatories to Intervenor | Ontario Energy Board | 2024-09-12 | 2024-09-12 | |
EB-2022-0325 | OEB Staff_IRs_UTR_phase_2_signed | Interrogatories to Intervenor | Ontario Energy Board | 2024-09-12 | 2024-09-12 | |
EB-2022-0325 | GCC_GCC Evidence_08292024 | Intervenor Evidence | Ontario Energy Board | 2024-08-29 | 2024-08-29 | |
EB-2022-0325 | LDC_Intervenor Evidence_Exhibit M1 LDC Transmission Group_20240829 | Intervenor Evidence | Ontario Energy Board | 2024-08-29 | 2024-08-29 | |
EB-2022-0325 | po4_OEB_UTR_20240729_signed | Procedural Order | Ontario Energy Board | 2024-07-29 | 2024-07-29 | |
EB-2022-0325 | GCC_LTR_Confirmation of Intent to File Evidence_20240716 | Correspondence | Ontario Energy Board | 2024-07-16 | 2024-07-16 | |
EB-2022-0325 | ENWIN_LTR_File_Evidence_20240716 | Correspondence | Ontario Energy Board | 2024-07-16 | 2024-07-16 | |
EB-2022-0325 | Entegrus Letter of Comment_20240710 | Letter of Comment | Ontario Energy Board | 2024-07-10 | 2024-07-10 | |
EB-2022-0325 | LDC Transmission Group - Letter_20240710 | Correspondence | Ontario Energy Board | 2024-07-10 | 2024-07-10 | |
EB-2022-0325 | po3_OEB_UTR_issues_list_20240705_signed | Procedural Order | Ontario Energy Board | 2024-07-05 | 2024-07-05 | |
EB-2022-0325 | GCC_LTR_Intent to File Evidence_20240528 | Correspondence | Ontario Energy Board | 2024-05-28 | 2024-05-28 | |
EB-2022-0325 | VECC Submissions_UTR Generic Hearing-Stage 2 re Draft Detailed Issue List_20240522 | Submission | Ontario Energy Board | 2024-05-22 | 2024-05-22 | |
EB-2022-0325 | ED_LtrIssuesList_20240522 | Submission | Ontario Energy Board | 2024-05-21 | 2024-05-21 | |
EB-2022-0325 | ENWIN Utilities Ltd_Intent to File Evidence_20240522 | Participation Request Letter | Ontario Energy Board | 2024-05-21 | 2024-05-21 | |
EB-2022-0325 | LPMA_SUB_ISSUES_20240521 | Submission | Ontario Energy Board | 2024-05-21 | 2024-05-21 | |
EB-2022-0325 | APPrO_ESC_Letter re Evidence and Issues List_20240521 | Submission | Ontario Energy Board | 2024-05-21 | 2024-05-21 | |
EB-2022-0325 | HONI_UTR Phase 2_Issues_List_Submission_20240521 | Submission | Ontario Energy Board | 2024-05-21 | 2024-05-21 | |
EB-2022-0325 | OEB transmission rates generic hearing issues intent to file evidence_20240521 | Correspondence | Ontario Energy Board | 2024-05-21 | 2024-05-21 | |
EB-2022-0325 | Joint submission_OEB transmission rates generic hearing issues list suggestions_20240521 | Submission | Ontario Energy Board | 2024-05-21 | 2024-05-21 | |
EB-2022-0325 | HONI_UTR Phase 2_Responses to Clarification Questions_20240513 | Interrogatory Response from Intervenor | Ontario Energy Board | 2024-05-13 | 2024-05-13 | |
EB-2022-0325 | Dec_on Issues 1-2 and 3_UTR_20240509_signed | Decision | Ontario Energy Board | 2024-05-09 | 2024-05-09 | |
EB-2022-0325 | OEB Staff_Draft Detailed Issues List_Issues 4 to 6_20240429 | Submission | Ontario Energy Board | 2024-04-29 | 2024-04-29 | |
EB-2022-0325 | po2_OEB_UTR_20240419_signed | Procedural Order | Ontario Energy Board | 2024-04-19 | 2024-04-19 | |
EB-2022-0325 | HONI_UTR Phase 2_Technical Conference Ltr_20240418 | Correspondence | Ontario Energy Board | 2024-04-17 | 2024-04-17 | |
EB-2022-0325 | GCC_Questions_Tech Conf_UTR Ph2_20240417 | Correspondence | Ontario Energy Board | 2024-04-17 | 2024-04-17 | |
EB-2022-0325 | AMPCO_Questions_Tech Conf_UTR Ph2_20240415 | Correspondence | Ontario Energy Board | 2024-04-15 | 2024-04-15 | |
EB-2022-0325 | Energy Probe_Questions UTR_TC_20240415 | Correspondence | Ontario Energy Board | 2024-04-15 | 2024-04-15 | |
EB-2022-0325 | SEC_Questions_Tech Conf_UTR Ph 2_20240415 | Correspondence | Ontario Energy Board | 2024-04-15 | 2024-04-15 | |
EB-2022-0325 | DRC_Questions_Tech Conf_UTR Ph 2_20240415 | Correspondence | Ontario Energy Board | 2024-04-15 | 2024-04-15 | |
EB-2022-0325 | LDC Transmission Group_Questions_Tech Conf_UTR Ph 2_20240415 | Correspondence | Ontario Energy Board | 2024-04-15 | 2024-04-15 | |
EB-2022-0325 | APPrO_ESC_Questions_Tech Conf_UTR Ph 2_20240415 | Correspondence | Ontario Energy Board | 2024-04-15 | 2024-04-15 | |
EB-2022-0325 | VECC_Questions_Tech Conf_UTR Ph 2_20240415 | Correspondence | Ontario Energy Board | 2024-04-15 | 2024-04-15 | |
EB-2022-0325 | LPMA_Questions_Tech Conf_UTR Ph 2_20240415 | Correspondence | Ontario Energy Board | 2024-04-15 | 2024-04-15 | |
EB-2022-0325 | HONI_UTR Phase 2_Background Report_Issues 4, 5 and 6_20240402 | Submission | Ontario Energy Board | 2024-04-02 | 2024-04-02 | |
EB-2022-0325 | DRC_LTR_Change of Address_20240308 | Correspondence | Ontario Energy Board | 2024-03-08 | 2024-03-08 | |
EB-2022-0325 | EDA_Sub on UTR Issues1_2_3_20240209 | Submission | Ontario Energy Board | 2024-02-09 | 2024-02-09 | |
EB-2022-0325 | CCC_Sub_UTRs_20240202 | Submission | Ontario Energy Board | 2024-02-02 | 2024-02-02 | |
EB-2022-0325 | SEC_SUB_UTR Phase 2_Issues 1_2 and 3_20240201 | Submission | Ontario Energy Board | 2024-02-01 | 2024-02-01 | |
EB-2022-0325 | HONI_UTR Ph2_SUB_Issues_1_2_and_3_20240201 | Submission | Ontario Energy Board | 2024-02-01 | 2024-02-01 | |
EB-2022-0325 | Energy Probe_Sub_UTR_20240201 | Submission | Ontario Energy Board | 2024-02-01 | 2024-02-01 | |
EB-2022-0325 | AMPCO_SUB_UTR_20240201 | Submission | Ontario Energy Board | 2024-02-01 | 2024-02-01 | |
EB-2022-0325 | AMPCO_CVR_Letter_UTR | Correspondence | Ontario Energy Board | 2024-02-01 | 2024-02-01 | |
EB-2022-0325 | DRC_Submissions re Issue 3_UTR_20240201 | Submission | Ontario Energy Board | 2024-02-01 | 2024-02-01 | |
EB-2022-0325 | LPMA_SUB_UTR_20240131 | Submission | Ontario Energy Board | 2024-01-31 | 2024-01-31 | |
EB-2022-0325 | VECC_SUB_Transmission Rates Phase2_20240130 | Submission | Ontario Energy Board | 2024-01-30 | 2024-01-30 | |
EB-2022-0325 | Intervention List_Updated_20240119 | Intervenor List | Ontario Energy Board | 2024-01-19 | 2024-01-19 | |
EB-2022-0325 | Halton_Name updates_Ph2_UTR_20240115 | Correspondence | Ontario Energy Board | 2024-01-15 | 2024-01-15 | |
EB-2022-0325 | APPrO_ESC_Update Contact_20240115 | Correspondence | Ontario Energy Board | 2024-01-15 | 2024-01-15 | |
EB-2022-0325 | Procedural Order 1_OEB_UTR_20231208 | Procedural Order | Ontario Energy Board | 2023-12-08 | 2023-12-08 | |
EB-2022-0325 | DRC_PartReq_GEN_UTR Ph 2_20231115 | Participation Request Letter | Ontario Energy Board | 2023-11-14 | 2023-11-14 | |
EB-2022-0325 | EDA_PartRQST_2023115 | Participation Request Letter | Ontario Energy Board | 2023-11-14 | 2023-11-14 | |
EB-2022-0325 | Energy Storage Canada_PartRQST_20231115 | Participation Request Letter | Ontario Energy Board | 2023-11-15 at 11:13 AM | ||
EB-2022-0325 | ED_PartRQST_Ph2_20231115 | Participation Request Letter | Ontario Energy Board | 2023-11-15 | 2023-11-15 | |
EB-2022-0325 | HONI_UTR Phase 2_Ltr_20231114 | Correspondence | Ontario Energy Board | 2023-11-15 | 2023-11-15 | |
EB-2022-0325 | Glencore Canada Corp_PartRQST_Ph2 conference_20231107 | Participation Request Letter | Ontario Energy Board | 2023-11-07 | 2023-11-07 | |
EB-2022-0325 | Notice_GEN_UTR Ph 2_En_20231027 | Notice of Hearing | Ontario Energy Board | 2023-10-27 | 2023-10-27 | |
EB-2022-0325 | Notice_GEN_UTR Ph 2_Fr_20231027 | Notice of Hearing | Ontario Energy Board | 2023-10-27 | 2023-10-27 | |
EB-2022-0325 | BoralexPartRQST_UTR Phase 2_20230728 | Participation Request Letter | Ontario Energy Board | 2023-07-28 | 2023-07-28 | |
EB-2022-0325 | VECC_PartRQST-Ph2 conference_20230126 | Participation Request Letter | Ontario Energy Board | 2023-01-26 | 2023-01-26 | |
EB-2022-0325 | SEC_PartRQSt_Ph2 Conference_20221222 | Participation Request Letter | Ontario Energy Board | 2023-01-23 | 2023-01-23 | |
EB-2022-0325 | NOTL_PartRQST_Ph2 conference_20221221 | Participation Request Letter | Ontario Energy Board | 2022-12-21 | 2022-12-21 | |
EB-2022-0325 | Northland Power_PartRQST_Ph2 conference_20221221 | Participation Request Letter | Ontario Energy Board | 2022-12-21 | 2022-12-21 | |
EB-2022-0325 | Hydro quebec_PartRQST_PH2 conference_20230110 | Participation Request Letter | Ontario Energy Board | 2023-01-10 | 2023-01-10 | |
EB-2022-0325 | Hydro one_PartRQST_20230110 | Participation Request Letter | Ontario Energy Board | 2023-01-10 | 2023-01-10 | |
EB-2022-0325 | Halton HILL_PartRQST_Ph2 conference_20230130 | Participation Request Letter | Ontario Energy Board | 2023-01-30 | 2023-01-30 | |
EB-2022-0325 | Enwin_PartRQST_PH2 conference_20230120 | Participation Request Letter | Ontario Energy Board | 2023-02-20 | 2023-02-20 | |
EB-2022-0325 | Entegrus_PartRQST_PH2 conference_20230117 | Participation Request Letter | Ontario Energy Board | 2023-01-17 | 2023-01-17 | |
EB-2022-0325 | EnergyProbe_PartRQST_Ph2 conference_20230104 | Participation Request Letter | Ontario Energy Board | 2023-01-04 | 2023-01-04 | |
EB-2022-0325 | Elexicon_PartRQST_PH2 conference_20230116 | Participation Request Letter | Ontario Energy Board | 2023-01-16 | 2023-01-16 | |
EB-2022-0325 | AMPCO_PartRQST_Ph2 conference_20230124 | Participation Request Letter | Ontario Energy Board | 2023-06-01 at 12:07 PM | ||
EB-2022-0325 | OEBLtr_UTR Issues Ph2_20221220 | Correspondence | Ontario Energy Board | 2022-12-20 | 2022-12-20 | |
Case Number | File Name | Document Type | Applicant | Issued By OEB | Received By OEB | Date Issued/Received |