Search Results for: Records - Case Number=EB-2012-0139 - 76 Records Found
The document result list has reached its limit of 10,000 records. Please refine your search criteria to view more records.
Sorting Your Search Results
The most recent documents automatically show at the top. To sort by different categories (e.g. by Document Type) click the column header. Click it again to switch between ascending/descending order.
Case Information
Click the case number to view details for that proceeding.
Case Number | File Name | Document Type | Applicant | Issued By OEB | Received By OEB | Date Issued/Received |
---|---|---|---|---|---|---|
EB-2012-0139 | dec_order_Cost Awards_20130621 | Decision and Order on Cost Awards | Innpower Corporation - Electricity Distributor | 2013-06-21 | 2013-06-21 | |
EB-2012-0139 | Innisfil_reporting requirement_20130530 | Correspondence | Innpower Corporation - Electricity Distributor | 2013-06-03 | 2013-06-03 | |
EB-2012-0139 | VECC_Cost Claim_Innisfil Hydro_20130507 | Cost Claim | Innpower Corporation - Electricity Distributor | 2013-05-07 | 2013-05-07 | |
EB-2012-0139 | SEC_Cost Claim_Innisfil Hydro_20130503 | Cost Claim | Innpower Corporation - Electricity Distributor | 2013-05-02 | 2013-05-02 | |
EB-2012-0139 | Energy Probe_Cost Claim_Innisfil Hydro_20130501 | Cost Claim | Innpower Corporation - Electricity Distributor | 2013-05-02 | 2013-05-02 | |
EB-2012-0139 | dec_order_Innisfil_20130425 | Decision and Order | Innpower Corporation - Electricity Distributor | 2013-04-25 | 2013-04-25 | |
EB-2012-0139 | Innisfil_2013_DRO_Tariff and Charges_corrected_Appendix I_20130419 | Draft Rate Order | Innpower Corporation - Electricity Distributor | 2013-04-19 | 2013-04-19 | |
EB-2012-0139 | Innsifil_cvr_ltr_Appendix I_corrected_20130417 | Draft Rate Order | Innpower Corporation - Electricity Distributor | 2013-04-17 | 2013-04-17 | |
EB-2012-0139 | Innisfil_Appendix I_2013 Draft Rate Order Tariff and Charges_20130417 | Draft Rate Order | Innpower Corporation - Electricity Distributor | 2013-04-17 | 2013-04-17 | |
EB-2012-0139 | Innisfil_cvr_ltr_Settlement Proposal_corrected_20130416 | Settlement Proposal | Innpower Corporation - Electricity Distributor | 2013-04-16 | 2013-04-16 | |
EB-2012-0139 | Innisfil_2013_CoS_Settlement Proposal_corrected_20130416 | Settlement Proposal | Innpower Corporation - Electricity Distributor | 2013-04-16 | 2013-04-16 | |
EB-2012-0139 | Innisfil_SMeter_20130315.xlsx | Interrogatory Response from Applicant | Innpower Corporation - Electricity Distributor | 2013-03-15 | 2013-03-15 | |
EB-2012-0139 | Innisfil_IRR_Supplemental_20130315.pdf | Interrogatory Response from Applicant | Innpower Corporation - Electricity Distributor | 2013-03-15 | 2013-03-15 | |
EB-2012-0139 | Innisfil_Costallocation_WF Equal 1_20130315.xlsm | Interrogatory Response from Applicant | Innpower Corporation - Electricity Distributor | 2013-03-15 | 2013-03-15 | |
EB-2012-0139 | Innisfil_Costallocation_Updated_20130315.xlsm | Interrogatory Response from Applicant | Innpower Corporation - Electricity Distributor | 2013-03-15 | 2013-03-15 | |
EB-2012-0139 | Innisfil_LFCDMAWF_20130315.xlsx | Interrogatory Response from Applicant | Innpower Corporation - Electricity Distributor | 2013-03-15 | 2013-03-15 | |
EB-2012-0139 | Innisfil_RRWF_20130315.xlsm | Interrogatory Response from Applicant | Innpower Corporation - Electricity Distributor | 2013-03-15 | 2013-03-15 | |
EB-2012-0139 | Innisifl_RTSR_Updated_20130315.xlsm | Interrogatory Response from Applicant | Innpower Corporation - Electricity Distributor | 2013-03-15 | 2013-03-15 | |
EB-2012-0139 | BdStaff_supplIR_LFCDMAWF_InnisfilHydro_20130227 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-03-01 | 2013-03-01 | 2013-03-01 |
EB-2012-0139 | VECC_IR_Supplementary_Innisfil_20130301 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-03-01 | 2013-03-01 | |
EB-2012-0139 | Energy Probe Supplemental IRs Innisfil Hydro_20130301 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-03-01 | 2013-03-01 | |
EB-2012-0139 | Energy Probe Supplemental IRs Innisfil Ltr OEB_20130301 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-03-01 | 2013-03-01 | |
EB-2012-0139 | SEC_Innisfil_SupIR_20130301.pdf | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-03-01 | 2013-03-01 | |
EB-2012-0139 | BdStaff_IR_Supplemental_Innisfil Hydro__20130228 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-02-28 | 2013-02-28 | 2013-02-28 |
EB-2012-0139 | Bdstaff_IR_IHDSL_cvr_ltr_20130228 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-02-28 | 2013-02-28 | 2013-02-28 |
EB-2012-0139 | BdStaff_IR_Supplemental_Innisfil Hydro__20130228 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-02-28 | 2013-02-28 | 2013-02-28 |
EB-2012-0139 | po2_Innisfil_20130220 | Procedural Order | Innpower Corporation - Electricity Distributor | 2013-02-20 | 2013-02-20 | |
EB-2012-0139 | Innisifl_RRWF_EB-2012-0139_20120214 Updated.xlsm | Interrogatory Response from Applicant | Innpower Corporation - Electricity Distributor | 2013-02-14 | 2013-02-14 | |
EB-2012-0139 | Innisifl_RRWF_Updated_20120214 | Interrogatory Response from Applicant | Innpower Corporation - Electricity Distributor | 2013-02-14 | 2013-02-14 | |
EB-2012-0139 | Innisfil_Response to IRs_20130214 | Interrogatory Response from Applicant | Innpower Corporation - Electricity Distributor | 2013-02-14 | 2013-02-14 | |
EB-2012-0139 | Innisfil_IRR_EB-2012-0139_20130213_CoverLetter.pdf | Correspondence | Innpower Corporation - Electricity Distributor | 2013-02-13 | 2013-02-13 | |
EB-2012-0139 | Innisfil_RRWF_V2_EB-2012-0139_20120213.xlsm | Interrogatory Response from Applicant | Innpower Corporation - Electricity Distributor | 2013-02-13 | 2013-02-13 | |
EB-2012-0139 | Innisfil_Chapter2_Bill Impacts_EB-2012-0139_20120213.xls | Interrogatory Response from Applicant | Innpower Corporation - Electricity Distributor | 2013-02-13 | 2013-02-13 | |
EB-2012-0139 | Ex1 Appendix 1 IR Ref OEB Staff-4 Bill Impacts_20130213.pdf | Interrogatory Response from Applicant | Innpower Corporation - Electricity Distributor | 2013-02-13 | 2013-02-13 | |
EB-2012-0139 | Innisfil_IRR_EB-2012-0139_20130213.pdf | Interrogatory Response from Applicant | Innpower Corporation - Electricity Distributor | 2013-02-13 | 2013-02-13 | |
EB-2012-0139 | Innisfil_Letter_Microfit fixed rate change_20130212.pdf | Correspondence | Innpower Corporation - Electricity Distributor | 2013-02-12 | 2013-02-12 | |
EB-2012-0139 | Bdstaff_IR_Innisfil_cvr_ltr_20130109 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-01-09 | 2013-01-09 | 2013-01-09 |
EB-2012-0139 | Board staff_IR_Innisfil_20130109 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-01-09 | 2013-01-09 | 2013-01-09 |
EB-2012-0139 | BOARD STAFF SUPPLEMENTAL INTERROGATORIES_20120114 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-01-14 | 2013-01-14 | 2013-01-14 |
EB-2012-0139 | Bdstaff_IR_Innisfil_cvr_ltr_supp IRs_20130114 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-01-14 | 2013-01-14 | 2013-01-14 |
EB-2012-0139 | SEC_Innisfil_IR_20130109 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-01-09 | 2013-01-09 | |
EB-2012-0139 | VECC_IRS_Innisfil_20130109 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-01-09 | 2013-01-09 | |
EB-2012-0139 | VECC_IRS_Innisfil_20130109 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-01-09 | 2013-01-09 | |
EB-2012-0139 | Energy Probe IRs Innisfil Hydro_20130104 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-01-04 | 2013-01-04 | |
EB-2012-0139 | Energy Probe_ Interrogatories Innisfil Ltr OEB_20130104 | Interrogatories to Applicant | Innpower Corporation - Electricity Distributor | 2013-01-04 | 2013-01-04 | |
EB-2012-0139 | po1_Innisfil_20121210 | Procedural Order | Innpower Corporation - Electricity Distributor | 2012-12-10 | 2012-12-10 | |
EB-2012-0139 | Innisfil_Affidavit_20121125.pdf | Affidavits of Service | Innpower Corporation - Electricity Distributor | 2012-11-25 | 2012-11-25 | |
EB-2012-0139 | VECC_INT_REQ_Innisfil_20121116 | Intervenor Request Letter | Innpower Corporation - Electricity Distributor | 2012-11-16 | 2012-11-16 | |
EB-2012-0139 | SEC_INT_REQ_Innisfil_20121116 | Intervenor Request Letter | Innpower Corporation - Electricity Distributor | 2012-11-16 | 2012-11-16 | |
EB-2012-0139 | noah_Innisfil_rev1_20121107 | Notice of Application and Notice of Hearing | Innpower Corporation - Electricity Distributor | 2012-11-13 | 2012-11-13 | |
EB-2012-0139 | Energy Probe_INT_REQ_InnisfilHydro_20121109 | Intervenor Request Letter | Innpower Corporation - Electricity Distributor | 2012-11-09 at 10:59 PM | ||
EB-2012-0139 | Energy Probe_INT_REQ_Innisfil _20121109 | Intervenor Request Letter | Innpower Corporation - Electricity Distributor | 2012-11-09 | 2012-11-09 | |
EB-2012-0139 | lod_noah_Innisfil_20121107 | Letter of Direction | Innpower Corporation - Electricity Distributor | 2012-11-07 | 2012-11-07 | |
EB-2012-0139 | Innisfil_Appl_Update_EB-2012-0139_20121024.pdf | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-10-24 | 2012-10-24 | |
EB-2012-0139 | Innisfil_2013_Load Forecast Data_20121023.xlsx | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-10-23 | 2012-10-23 | |
EB-2012-0139 | Innisfil_CVRLTR_Incomplete_20121023.pdf | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-10-23 | 2012-10-23 | |
EB-2012-0139 | Innisfil_APPL_Update_20121024.pdf | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-10-24 | 2012-10-24 | |
EB-2012-0139 | Ack_ltr_Incomplete_Innisfil_20121009 | Correspondence | Innpower Corporation - Electricity Distributor | 2012-10-09 | 2012-10-09 | |
EB-2012-0139 | Ack_Ltr_Innisfil_20120920 | Acknowledgement Letter | Innpower Corporation - Electricity Distributor | 2012-09-20 | 2012-09-20 | |
EB-2012-0139 | Innisfil_EB-2012-0139_Rev_Reqt_Work_Form_20120919 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-19 | 2012-09-19 | |
EB-2012-0139 | Innisfil_2013_Test_year_IncomeTax_PILs_Workform_20120919 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-19 | 2012-09-19 | |
EB-2012-0139 | Innisfil_2013_Test_year_IncomeTax_PILs_Workform_20120919 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-19 | 2012-09-19 | |
EB-2012-0139 | Innisfil_EB-2012-0139_Rev_Reqt_Work_Form_20120919 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-19 | 2012-09-19 | |
EB-2012-0139 | Innisfil_EB-2012-0139_GEA Rate Rider Calculation_20120913 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-13 | 2012-09-13 | |
EB-2012-0139 | Innisfil_EB-2012-0139_2013_EDDVAR_Continuity_Schedule_20120913 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-13 | 2012-09-13 | |
EB-2012-0139 | Innisfil_Cost_Allocation_Model_20120913 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-13 | 2012-09-13 | |
EB-2012-0139 | Innisfil _EDDVAR_Continuity_Schedule_20120913 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-13 | 2012-09-13 | |
EB-2012-0139 | Innisfil _Cost_Allocation_Model_Final Run_20120913 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-13 | 2012-09-13 | |
EB-2012-0139 | Innisfil _Chapter2_Appendices_20120913 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-13 | 2012-09-13 | |
EB-2012-0139 | GEA Rate Rider Calculation_20120913 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-13 | 2012-09-13 | |
EB-2012-0139 | Innisfil_RTSR MODEL_20120913 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-13 | 2012-09-13 | |
EB-2012-0139 | Innisfil_EB-2012-0139_IHDSL_2013_Chapter2_Appendices_20120913 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-13 | 2012-09-13 | |
EB-2012-0139 | Innisfil_RTSR MODEL_V3_20120913.pdf | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-13 | 2012-09-13 | |
EB-2012-0139 | Cover_Letter_EB-2012-0139_2013_Rate_Application_20120913 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-13 | 2012-09-13 | |
EB-2012-0139 | Innisfil_APPL_EB-2012-0139_20120913 | Application and Evidence | Innpower Corporation - Electricity Distributor | 2012-09-13 | 2012-09-13 | |
EB-2012-0139 | Innisfil_Corresp_20120828 | Correspondence | Innpower Corporation - Electricity Distributor | 2012-08-28 | 2012-08-28 | |
Case Number | File Name | Document Type | Applicant | Issued By OEB | Received By OEB | Date Issued/Received |