EB-2017-0035
|
DO on Cost Awards-Embrun_20180214
|
Decision and Order on Cost Awards
|
2018-02-14
|
|
2018-02-14
|
EB-2017-0035
|
CHEI 2018_Tariff of Rates and Charges_RevisedRateOrder_20180206
|
Rate Order
|
2018-02-06
|
|
2018-02-06
|
EB-2017-0035
|
CooperativeHydroEmbrun_Revised Rate Order_20180206
|
Rate Order
|
2018-02-06
|
|
2018-02-06
|
EB-2017-0035
|
CHEI 2018 Settlement Proposal_20180206
|
Settlement Proposal
|
|
2018-02-06
|
2018-02-06
|
EB-2017-0035
|
CHEI 2018 Cost of Power Calcs 20180206
|
Settlement Proposal
|
|
2018-02-06
|
2018-02-06
|
EB-2017-0035
|
VECC Cost Claim_Embrun_20180201
|
Cost Claim
|
|
2018-02-02
|
2018-02-02
|
EB-2017-0035
|
CHEI 2018_Proposed Tariff Sheet_Settlement_OEBSTAFF 20180129.pdf
|
Settlement Proposal
|
|
2018-01-30
|
2018-01-30
|
EB-2017-0035
|
CHEI 2018 Settlement Proposal_20180129.pdf
|
Settlement Proposal
|
|
2018-01-30
|
2018-01-30
|
EB-2017-0035
|
CHEI 2018 Cost of Power Calcs 20180129.pdf
|
Settlement Proposal
|
|
2018-01-30
|
2018-01-30
|
EB-2017-0035
|
Embrun_settlement proposal_cover letter_20180130
|
Settlement Proposal
|
|
2018-01-30
|
2018-01-30
|
EB-2017-0035
|
Dec_Rate Order_CooperativeEmbrun_20180125
|
Decision and Order
|
2018-01-25
|
|
2018-01-25
|
EB-2017-0035
|
exhibit list_Embrun_settlement hearing_20180112
|
Exhibit List
|
|
|
2018-01-22 at 3:23 PM
|
EB-2017-0035
|
EX_K1.1_20180112
|
Exhibits
|
|
2018-01-12
|
2018-01-12
|
EB-2017-0035
|
CHEI 2018 Settlement Proposal_20180117
|
Settlement Proposal
|
|
2018-01-17
|
2018-01-17
|
EB-2017-0035
|
Hydro Embrun_transcript_Settlement Presentation_vol 1_20180112
|
Transcripts
|
|
2018-01-12
|
2018-01-12
|
EB-2017-0035
|
CHEI 2018_Proposed Tariff Sheet_Settlement_20180110.XLSX
|
Settlement Proposal
|
|
2018-01-11
|
2018-01-11
|
EB-2017-0035
|
OEB Ltr_PresentationDayConfirmation_Embrun_20170104
|
Correspondence
|
2018-01-04
|
|
2018-01-04
|
EB-2017-0035
|
CHEI 2018_TESI Load Forecasting Model_SettlementP_2017122
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI 2018_DVA_Continuity Schedule_SettlementP_2017122
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI 2018_Cost Allocation Model_SettlementP_2017122
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI 2018_PILs Workform_SettlementP_2017122
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI 2018_Rev Reqt Work Form_SettlementP_2017122
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI 2018_RTSR Workform_SettlementP_2017122
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI 2018_Filing Requirement Chapter 2_Appendices_SettlementP_2017122
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI 2018_Tariff Schedule and Bill Impact Model V2_SettlementP_2017122
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI 2018_Benchmarking_Forecast_SettlementP_2017122
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI 2018_GA Analysis Workform SettlementP_20171222
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI 2018_LRAMVA_Work Form V2_SettlementP_20171222
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI 2018_Proposed Tariff Sheet_SettlementP-20171222
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI 2018_Cost of Power Calculations_20171222
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI_Response_ADR Clarification Questions_20171222
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI_SettlementP_20171222
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
CHEI_SettlementP_cvrltr_20171222
|
Settlement Proposal
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0035
|
ExtensionLetter_SettlementProposal_CooperativeHydroEmbrun_20171221
|
Correspondence
|
2017-12-21
|
|
2017-12-21
|
EB-2017-0035
|
CHEI_LTR_Embrun_20171220
|
Correspondence
|
2017-12-21
|
|
2017-12-21
|
EB-2017-0035
|
Interim Rate Order_CooperativeHydroEmbrun_20171219
|
Interim rate order
|
2017-12-19
|
|
2017-12-19
|
EB-2017-0035
|
CHEI_LTR_Interim Rates_Req_20171213
|
Correspondence
|
|
2017-12-13
|
2017-12-13
|
EB-2017-0035
|
CHEI_Respnse_Ltr of Comment_P Carriere_20171113
|
Correspondence
|
|
2017-11-14
|
2017-11-14
|
EB-2017-0035
|
CHEI_Response_ltr of Comment_P Roy_Redacted_20171113
|
Correspondence
|
|
2017-11-14
|
2017-11-14
|
EB-2017-0035
|
CHEI_2018 Tariff Schedule_Bill Impact Model V2_20171114
|
Interrogatory Response from Applicant
|
|
2017-11-14
|
2017-11-14
|
EB-2017-0035
|
issues list_dec_Embrun_20171113
|
Decision
|
2017-11-13
|
|
2017-11-13
|
EB-2017-0035
|
Board staff_issues list_Coop Hydro_20171110
|
Submission
|
|
2017-11-10
|
2017-11-10
|
EB-2017-0035
|
CHEI 2018_Tariff_Schedule_and_Bill_Impact_Model_V2_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
2016 Final Results Cooperative Hydro Embrun_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
CHEI 2018_DVA_Continuity_Schedule_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
CHEI 2018 Update of Demand Data_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
CHEI 2018 TESI Load Forecasting Model_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
CHEI 2018 RTSR Workform_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
CHEI 2018 Rev Reqt Work Form_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
CHEI 2018 Proposed Tariff Sheet_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
CHEI 2018 PILs Workform_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
CHEI 2018 LRAMVA_Work_Form_v 2_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
CHEI 2018 GA_Analysis Workform_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
CHEI 2018 Cost Allocation Model_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
CDM Plan - HHI CHE HYD - Approved - IESO 20170802_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
Final Results Report_Cooperative Hydro Embrun Inc_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
Response to OEB Staff Interrogatories_20171103
|
Interrogatory Response from Applicant
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0035
|
PO3_Embrun_CoS_20171031
|
Procedural Order
|
2017-10-31
|
|
2017-10-31
|
EB-2017-0035
|
Community_Meeting_Summary_Embrun-Final_French_20171010.pdf
|
Submission
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0035
|
Community_Meeting_Summary_Embrun_Final_English_20171010.pdf
|
Submission
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0035
|
PO2_Embrun_20171010
|
Procedural Order
|
2017-10-10
|
|
2017-10-10
|
EB-2017-0035
|
EB-2017-0035-CHEI_Delay in filing responses to IRs.pdf
|
Correspondence
|
|
2017-10-06
|
2017-10-06
|
EB-2017-0035
|
VECC IRQ CoEmbrun0085_10042017.pdf
|
Interrogatories to Applicant
|
|
2017-10-04
|
2017-10-04
|
EB-2017-0035
|
OEBStaff_IR_CHEI_20170929.pdf
|
Interrogatories to Applicant
|
|
2017-09-29
|
2017-09-29
|
EB-2017-0035
|
2017_Tariff_Schedule_and_Bill_Impact_Model_V1.02_OEBstaff_IR.xlsm
|
Interrogatories to Applicant
|
|
2017-09-29
|
2017-09-29
|
EB-2017-0035
|
Ack Ltr_letter of comment_Roy_20170926
|
Acknowledgement Letter
|
2017-09-26
|
|
2017-09-26
|
EB-2017-0035
|
Letter of Comment - Cooperative Hydro Embrun _20170919_Redacted
|
Letter of Comment
|
|
2017-09-19
|
2017-09-19
|
EB-2017-0035
|
PRoy_LtrComment_REDACTED_20170920
|
Letter of Comment
|
|
2017-09-20
|
2017-09-20
|
EB-2017-0035
|
PO1_Embrun_20170921
|
Procedural Order
|
2017-09-21
|
|
2017-09-21
|
EB-2017-0035
|
VECC N of I EB 2017-0035_20170828
|
Intervenor Request Letter
|
|
2017-08-28
|
2017-08-28
|
EB-2017-0035
|
CHEI Affidavit of Service_20170814
|
Affidavits of Service
|
|
2017-08-14
|
2017-08-14
|
EB-2017-0035
|
LoD_Embrun_20170811
|
Letter of Direction
|
2017-08-11
|
|
2017-08-11
|
EB-2017-0035
|
noa_Embrun_FR_20170811
|
Notice
|
2017-08-11
|
|
2017-08-11
|
EB-2017-0035
|
noa_Embrun_20170811
|
Notice
|
2017-08-11
|
|
2017-08-11
|
EB-2017-0035
|
EB-2018-0035 CHEI Ex 9 DVA rev 20170614.pdf
|
Application and Evidence
|
|
2017-06-22
|
2017-06-22
|
EB-2017-0035
|
CHEI 2018_Filing_Requirements_Chapter2_Appendices 20170614
|
Application and Evidence
|
|
2017-06-22
|
2017-06-22
|
EB-2017-0035
|
EB-2018-0035 CHEI Ex 9 DVA rev 20170614
|
Application and Evidence
|
|
2017-06-14
|
2017-06-14
|
EB-2017-0035
|
EB-2018-0035 CHEI Ex 8 Rate Design rev 20170614
|
Application and Evidence
|
|
2017-06-14
|
2017-06-14
|
EB-2017-0035
|
EB-2018-0035 CHEI Ex 3 Revenues rev 20170614
|
Application and Evidence
|
|
2017-06-14
|
2017-06-14
|
EB-2017-0035
|
EB-2018-0035 CHEI Ex 2 Rate Base rev 20170614
|
Application and Evidence
|
|
2017-06-14
|
2017-06-14
|
EB-2017-0035
|
EB-2018-0035 CHEI Ex 1 Administrative Documents rev 20170614
|
Application and Evidence
|
|
2017-06-14
|
2017-06-14
|
EB-2017-0035
|
Incomplete Letter_CooperativeHydroEmbrun_2017060
|
Application and Evidence
|
|
2017-06-14
|
2017-06-14
|
EB-2017-0035
|
Incomplete Letter_CooperativeHydroEmbrun_20170601
|
Correspondence
|
2017-06-01
|
|
2017-06-01
|
EB-2017-0035
|
Ack Letter_Embrun_20170502
|
Acknowledgement Letter
|
2017-05-02
|
|
2017-05-02
|
EB-2017-0035
|
Final 2015 Annual Verified Results Report_20160630
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI 2018_COS_Checklist_Final_20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI 2018 LRAMVA WorkForm 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI 2018 Benchmarking_Forecast 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
Final Results Report_Cooperative Hydro Embrun Inc
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI 2018_OEB Chapter2_Appendices 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI 2018_DVA_Continuity_Schedule_20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI 2018 Update of Demand Data 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI 2018 Tariff_Schedule_and_Bill_Impact 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI 2018 RTSR Workform 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI 2018 Rev Reqt Work Form 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI 2018 PILs Workform 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI 2018 Cost Allocation Model 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI 2018 Load Forecasting Model 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI Ex 9 DVA 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI Ex 8 Rate Design 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI Ex 7 Cost Allocation 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI Ex 6 Revenue Requirement 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI Ex 5 Cost of Capital 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI Ex 4 Operating Expenses 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI Ex 3 Revenues 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI Ex 2 Rate Base 20170501
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI Ex 1 Administrative Documents 20170501.pdf
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|
EB-2017-0035
|
CHEI appl RATES Cover letter 2017050
|
Application and Evidence
|
|
2017-05-01
|
2017-05-01
|