EB-2017-0024
|
Dec_Order_on Cost Awards_Alectra Utilities_20180615
|
Decision and Order on Cost Awards
|
2018-06-15
|
|
2018-06-15
|
EB-2017-0024
|
AMPCO_cost claim_20180511
|
Cost Claim
|
|
2018-05-23
|
2018-05-23
|
EB-2017-0024
|
Alectra_CostsObj_20180517
|
Cost Claim Objection
|
|
2018-05-17
|
2018-05-17
|
EB-2017-0024
|
CCC_CostClaim_Alectra2018_20180516
|
Cost Claim
|
|
2018-05-16
|
2018-05-16
|
EB-2017-0024
|
BOMA_Cost_Claim_20180510
|
Cost Claim
|
|
2018-05-10
|
2018-05-10
|
EB-2017-0024
|
Sec_Cost Claim_20180510
|
Cost Claim
|
|
2018-05-10
|
2018-05-10
|
EB-2017-0024
|
VECC Cost Claim_ Alectra_20180509
|
Cost Claim
|
|
2018-05-09
|
2018-05-09
|
EB-2017-0024
|
Decision_Rate Order_Alectra_20180503
|
Rate Order
|
2018-05-03
|
|
2018-05-03
|
EB-2017-0024
|
Decision_Rate Order_Alectra_20180503
|
Decision
|
2018-05-03
|
|
2018-05-03
|
EB-2017-0024
|
Alectra_Attach 11_DRO_IRM model BRZ_20180427
|
Rate Model
|
|
2018-04-27
|
2018-04-27
|
EB-2017-0024
|
Alectra_Attach 21_DRO ReplySUB_Foregone Revenue Calculation_All RZs_20180427
|
Submission
|
|
2018-04-27
|
2018-04-27
|
EB-2017-0024
|
Alectra_Attach 20_DRO ReplySUB_ICM Model_ERZ_20180427.
|
Submission
|
|
2018-04-27
|
2018-04-27
|
EB-2017-0024
|
Alectra_Attach 18_DRO ReplySUB_IRM model_ERZ_20180427
|
Submission
|
|
2018-04-27
|
2018-04-27
|
EB-2017-0024
|
Alectra_Attach 14_DRO ReplySUB_IRM model_PRZ_20180427
|
Submission
|
|
2018-04-27
|
2018-04-27
|
EB-2017-0024
|
Alectra_ReplySUB_Attach 11_DRO Reply_Cost_Allocation 2018_Model_V3_4_HRZ_20180427
|
Submission
|
|
2018-04-27
|
2018-04-27
|
EB-2017-0024
|
Alectra_Attach 6_DRO Reply_Cost_Allocation 2018_Model_V3_4_HRZ_20180427
|
Submission
|
|
2018-04-27
|
2018-04-27
|
EB-2017-0024
|
Alectra_Attach 5_DRO Reply_Bill Impacts_Tariff Sheet_HRZ_20180427
|
Submission
|
|
2018-04-27
|
2018-04-27
|
EB-2017-0024
|
Alectra_Attach 3_DRO Reply_PILs Workform 2018_HRZ_20180427
|
Submission
|
|
2018-04-27
|
2018-04-27
|
EB-2017-0024
|
Alectra_Attach 2a_DRO Reply_2018 Cost of Power Calculation_20180427
|
Submission
|
|
2018-04-27
|
2018-04-27
|
EB-2017-0024
|
Alectra_Attach 2_DRO Reply_ Revenue Requirement Work Form 2018_V7.02_HRZ_20180427
|
Submission
|
|
2018-04-27
|
2018-04-27
|
EB-2017-0024
|
Alectra_DRO Reply 2018 Tariff of Rates and Charges_All RZs_20180427
|
Submission
|
|
2018-04-27
|
2018-04-27
|
EB-2017-0024
|
AlectraUtilities_DRF_RO_ReplySUB_20180427
|
Submission
|
|
2018-04-27
|
2018-04-27
|
EB-2017-0024
|
Alectra Utilities OEB Staff DRO Submission_20180423
|
Submission
|
|
2018-04-23
|
2018-04-23
|
EB-2017-0024
|
Attach 22_DRO_Renewable Generation Calculation_All RZs
|
Rate Model
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 21_DRO_Foregone Revenue Calculation_All RZs
|
Rate Model
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 20_DRO_ICM Model_ERZ
|
Rate Model
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 19_DRO_LRAMVA Workform_ERZ
|
Rate Model
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 18a_DRO_RGM_ERZ
|
Rate Model
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 18_DRO_IRM model_ERZ
|
Rate Model
|
|
2018-04-17
|
2018-04-17
|
EB-2017-0024
|
Attach 16_DRO_ICM Model_PRZ.xlsm
|
Rate Model
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 15_DRO_LRAMVA Workform_PRZ
|
Draft Rate Order
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 14_DRO_IRM model_PRZ
|
Draft Rate Order
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 12_DRO__ICM Model_BRZ
|
Draft Rate Order
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 11a_DRO_RGM_BRZ
|
Draft Rate Order
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 11_DRO_IRM model BRZ
|
Draft Rate Order
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 9_DRO_LRAMVA Workform_HRZ
|
Draft Rate Order
|
|
2018-04-17
|
2018-04-17
|
EB-2017-0024
|
Attach 8_DRO_RTSR Work Form_HRZ
|
Draft Rate Order
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 6_DRO_Cost_Allocation 2018_Model_V3_4_HRZ
|
Draft Rate Order
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 5_DRO_Bill Impacts_Tariff Sheet_HRZ
|
Draft Rate Order
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 4_DRO_IRM Model HRZ
|
Draft Rate Order
|
|
2018-04-17
|
2018-04-17
|
EB-2017-0024
|
Attach 3_DRO_PILs Workform 2018_HRZ
|
Draft Rate Order
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 2a_DRO_2018 Cost of Power Calculation
|
Draft Rate Order
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Attach 2_DRO_ Revenue Requirement Work Form 2018_V7.02_HRZ
|
Draft Rate Order
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
AlectraUtilitiesCorporation_DRO_2018EDR_ATTACH 10-22_20180416
|
Draft Rate Order
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
Alectra_DraftRateOrder_20180416
|
Draft Rate Order
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
AlectraUtilitiesCorporation_DRO_2018EDR_ATTACH 1-9_20180416
|
Draft Rate Order
|
|
2018-04-16
|
2018-04-16
|
EB-2017-0024
|
OEB_Errata_Ltr_dec_order_Alectra_20180406
|
Decision and Order
|
2018-04-06
|
|
2018-04-06
|
EB-2017-0024
|
dec_order_Alectra_rev_20180406
|
Decision and Order
|
2018-04-06
|
|
2018-04-06
|
EB-2017-0024
|
dec_order_Alectra_20180405
|
Decision and Order
|
2018-04-05
|
|
2018-04-05
|
EB-2017-0024
|
Alectra_ReplySUB_20180130
|
Submission
|
|
2018-01-30
|
2018-01-30
|
EB-2017-0024
|
BOMA_ArgumentSUB_20170117
|
Submission
|
|
2018-01-17
|
2018-01-17
|
EB-2017-0024
|
VECC_ArgumentSUB_ALECTRA_20180116
|
Submission
|
|
2018-01-17
|
2018-01-17
|
EB-2017-0024
|
PWU_ArgumentSUB_Alectra_20180116
|
Submission
|
|
2018-01-16
|
2018-01-16
|
EB-2017-0024
|
AMPCO_ArgumentSUB_Alectra_20170116
|
Submission
|
|
2018-01-17
|
2018-01-17
|
EB-2017-0024
|
SEC_ArgumentSUB_Alectra_20180116
|
Submission
|
|
2018-01-17
|
2018-01-17
|
EB-2017-0024
|
CCC_ArgumentSUB_Alectra_20180116
|
Submission
|
|
2018-01-17
|
2018-01-17
|
EB-2017-0024
|
OEBStaff_ArgumentSUB_Alectra_20180116
|
Submission
|
|
2018-01-17
|
2018-01-17
|
EB-2017-0024
|
OEB_BOMASubmissionDelay_20180116
|
Correspondence
|
2018-01-16
|
|
2018-01-16
|
EB-2017-0024
|
Alectra_ARG Chief_20171222
|
Applicant Argument in Chief
|
|
2017-12-22
|
2017-12-22
|
EB-2017-0024
|
dec_partial_accounting order_Alectra_20171220
|
Decision
|
2017-12-20
|
|
2017-12-20
|
EB-2017-0024
|
VECC_change in Counsel_20171220
|
Correspondence
|
|
2017-12-20
|
2017-12-20
|
EB-2017-0024
|
JT2.19_Attach 1_Updated Table 55 Material Projects ERZ 2017_2022_20171215
|
Undertaking Responses
|
|
2017-12-15
|
2017-12-15
|
EB-2017-0024
|
JTStaff-8_Attach 3_LRAMVA Workform ERZ SL_20171215
|
Undertaking Responses
|
|
2017-12-15
|
2017-12-15
|
EB-2017-0024
|
JTStaff-8_Attach 2_LRAMVA Workform PRZ SL_20171215
|
Undertaking Responses
|
|
2017-12-15
|
2017-12-15
|
EB-2017-0024
|
JTStaff-8_Attach 1_LRAMVA Workform HRZ SL_20171215
|
Undertaking Responses
|
|
2017-12-15
|
2017-12-15
|
EB-2017-0024
|
JTStaff-5_PRZ-Staff-5_Attach 2_IRM RGM PowerStream RZ_20171215
|
Undertaking Responses
|
|
2017-12-15
|
2017-12-15
|
EB-2017-0024
|
JTStaff 3_Attach 1_IRM Model Horizon Utilities RZ_20171215
|
Undertaking Responses
|
|
2017-12-15
|
2017-12-15
|
EB-2017-0024
|
JTStaff-5_PRZ-Staff-5_Attach 2_IRM Model PowerStream RZ_20171215
|
Undertaking Responses
|
|
2017-12-15
|
2017-12-15
|
EB-2017-0024
|
JTStaff-2_Attach 1_IRM Model Enersource RZ_20171215
|
Undertaking Responses
|
|
2017-12-15
|
2017-12-15
|
EB-2017-0024
|
JTStaff-5_Attachment1_GA Workform_20171215
|
Undertaking Responses
|
|
2017-12-15
|
2017-12-15
|
EB-2017-0024
|
JTStaff-1 - 2018 Cost of Power Calculation_20171215
|
Undertaking Responses
|
|
2017-12-15
|
2017-12-15
|
EB-2017-0024
|
JT2.20_Attach_ERZ-AMPCO-17-Appendix D_20171215
|
Undertaking Responses
|
|
2017-12-15
|
2017-12-15
|
EB-2017-0024
|
JT2.16_Attach_ERZ-AMPCO-6_AppendixB_20171215
|
Undertaking Responses
|
|
2017-12-15
|
2017-12-15
|
EB-2017-0024
|
JT2.11_Attach_PRZ-AMPCO-18_20171215
|
Undertaking Responses
|
|
2017-12-15
|
2017-12-15
|
EB-2017-0024
|
AlectraUtilities_TCUndertakings_20171215
|
Undertaking Responses
|
|
2017-12-15
|
2017-12-15
|
EB-2017-0024
|
VECC_Alectra0024_SubDefAccts_20171208
|
Submission
|
|
2017-12-08
|
2017-12-08
|
EB-2017-0024
|
Alectra_Submission re Capitalization Accounts_20171208
|
Submission
|
|
2017-12-07
|
2017-12-07
|
EB-2017-0024
|
SEC_Submission_20171208
|
Submission
|
|
2017-12-07
|
2017-12-07
|
EB-2017-0024
|
BOMA_Submission_20171207
|
Submission
|
|
2017-12-07
|
2017-12-07
|
EB-2017-0024
|
Alectra-Staff Submission on Recording Details_20171207
|
Submission
|
|
2017-12-07
|
2017-12-07
|
EB-2017-0024
|
Transcript_Day 2_Alectra Utilities_TC_2071201
|
Transcripts
|
|
2017-12-01
|
2017-12-01
|
EB-2017-0024
|
Transcript_day1_Alectra Utilities_TC_20171130.doc
|
Transcripts
|
|
2017-11-30
|
2017-11-30
|
EB-2017-0024
|
Alectra_OEB Staff TC Clarifications_20171128
|
Submission
|
|
2017-11-28
|
2017-11-28
|
EB-2017-0024
|
Dec_Issues List_PO3_Alectra_20171117
|
Decision
|
2017-11-17
|
|
2017-11-17
|
EB-2017-0024
|
Dec_Issues List_PO3_Alectra_20171117
|
Procedural Order
|
2017-11-17
|
|
2017-11-17
|
EB-2017-0024
|
BOMA_Correspondence_20171110
|
Submission
|
|
2017-11-10
|
2017-11-10
|
EB-2017-0024
|
City of Hamilton_Hearing_Issues List_20171110
|
Correspondence
|
|
2017-11-10
|
2017-11-10
|
EB-2017-0024
|
CCC_Alectra_Sub_ProcessIssues_20171110
|
Submission
|
|
2017-11-10
|
2017-11-10
|
EB-2017-0024
|
SEC_Sub_re Hearing _20171110
|
Submission
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
CoH Letter_Sub_201711-10
|
Submission
|
|
2017-11-10
|
2017-11-10
|
EB-2017-0024
|
AMPCO_LTR_Hearing_20171110.pdf
|
Submission
|
|
2017-11-10
|
2017-11-10
|
EB-2017-0024
|
VECC_Oral Issues Submission_20171110
|
Submission
|
|
2017-11-10
|
2017-11-10
|
EB-2017-0024
|
Alectra_LTR_Form Of Hearing_20171110.pdf
|
Correspondence
|
|
2017-11-10
|
2017-11-10
|
EB-2017-0024
|
OEB_Ltr_AlectraltrWrittenvsOralIssues_20171110
|
Correspondence
|
|
2017-11-10
|
2017-11-10
|
EB-2017-0024
|
Alectra_LTR_Draft_Issues_List_20171106
|
Correspondence
|
|
2017-11-06
|
2017-11-06
|
EB-2017-0024
|
Alectra_ltr_Redraft issues list_20171106
|
Correspondence
|
|
2017-11-06
|
2017-11-06
|
EB-2017-0024
|
Alectra_SettlementLtr_20171103
|
Correspondence
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0024
|
Alectra_Ltr_Submissions_on IssuesList_20171103
|
Draft Rate Order
|
|
2017-11-06
|
2017-11-06
|
EB-2017-0024
|
CoH _Submissions On issues list_20171103
|
Submission
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0024
|
BOMA_submission on issues list_20171103
|
Submission
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0024
|
CCC_Submission on Issues List_20171103
|
Submission
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0024
|
AMPCO_Submission on Draft Issues List_20171103
|
Submission
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0024
|
VECC_Issues List Submission_Alectra 20171103
|
Submission
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0024
|
SEC_Issues List Submissions_20171103
|
Submission
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0024
|
BdStaff_Alectra ltr Revised Draft Issues List__20171103
|
Submission
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0024
|
Alectra_CORR_Re Settlement Conference_20171103
|
Correspondence
|
|
2017-11-03
|
2017-11-03
|
EB-2017-0024
|
City of Hamilton_Letter_20171024
|
Correspondence
|
|
2017-10-24
|
2017-10-24
|
EB-2017-0024
|
SEC_ Supp_Interrogatories_20171025
|
Interrogatories to Applicant
|
|
2017-10-24
|
2017-10-24
|
EB-2017-0024
|
PO2_Alectra_20171024
|
Procedural Order
|
2017-10-24
|
|
2017-10-24
|
EB-2017-0024
|
BOMA_DEC_UND_20171024
|
Declaration and Undertakings
|
|
2017-10-24
|
2017-10-24
|
EB-2017-0024
|
OEB Staff_Issues list_ Alectra_20171018
|
Submission
|
|
2017-10-18
|
2017-10-18
|
EB-2017-0024
|
dec on Appeal_intervenor status_20171013
|
Decision
|
2017-10-13
|
|
2017-10-13
|
EB-2017-0024
|
ERZ-AMPCO-3_Attach 1_2018 Capital Project Listing Enersource RZ_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
ERZ-AMPCO-9_Attachment_1_Live _Model_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
ERZ-AMPCO-13_Live Model_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
ERZ-Staff-19_Attach 1_LRAMVA Work Form Enersource RZ_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
G-Staff-1_Attach 1_GA Workform_Brampton Rate Zone_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
G-Staff-2_Attach 2_IRM RGM PowerStream RZ_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
G-Staff-2_Attach 2_IRM Model PowerStream RZ_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
G-Staff-2_Attach 1_IRM RGM Brampton RZ_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
G-Staff-2_Attach 1_IRM Model Brampton RZ_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
G-Staff-1_Attach 4_GA Workform_PowerStream Rate Zone_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
G-Staff-1_Attach 3_GA Workform_Horizon Utilities Rate Zone_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
G-Staff-1_Attach 2_GA Workform_Enersource Rate Zone_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
G-Staff-2_Attach 3_IRM Model Enersource RZ_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
G-Staff-2_Attach 3_IRM RGM Enersource RZ_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
HRZ-Staff-2_Attach 1_2018 Annual Filing COP Calculation_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
HRZ-Staff-14_Final_Attachment_LRAMVA_Work_Form - Horizon Utilities RZ_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
HRZ-Staff-18_Attach 1_IRM Model Horizon Utilities RZ_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
PRZ-AMPCO-6_Attach 1_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
PRZ-Staff-21_Attach 1_LRAMVA Work Form PowerStream RZ_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
ERZ-Staff-18_Attach 2_2011-2014 Enersource Persistence Savings_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
ERZ-Staff-18_Attach 1_2011-2014 Final Results Report Enersource_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
Alectra_IRR_BOMA_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
Alectra_IRR_Board Staff_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
Alectra_IRR_VECC_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
Alectra_IRR_AMPCO_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
Alectra_IRR-COH_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
Alectra Utilities_ Cover Letter IRR_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
Alectra_IRR_CCC_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
Alectra_IRR_SEC_20171011
|
Interrogatory Response from Applicant
|
|
2017-10-11
|
2017-10-11
|
EB-2017-0024
|
OEB Staff Interrogatories_Alectra_20170918
|
Interrogatories to Applicant
|
|
2017-09-18
|
2017-09-18
|
EB-2017-0024
|
AMPCO_IR_Alectra_20170920_rev.pdf
|
Interrogatories to Intervenor
|
|
2017-09-27
|
2017-09-27
|
EB-2017-0024
|
City of Hamilton_Support of PWU IntrvREQ_Alectra_20170921
|
Correspondence
|
|
2017-09-21
|
2017-09-21
|
EB-2017-0024
|
BOMA_ltr_Corrections to IR_Alectra_20170921
|
Interrogatories to Applicant
|
|
2017-09-21
|
2017-09-21
|
EB-2017-0024
|
ERZ-AMPCO-17-Appendix D_20170921
|
Interrogatories to Applicant
|
|
2017-09-21
|
2017-09-21
|
EB-2017-0024
|
ERZ-AMPCO-10-Appendix C_20170921
|
Interrogatories to Applicant
|
|
2017-09-21
|
2017-09-21
|
EB-2017-0024
|
ERZ-AMPCO-IR-6-Appendix B_20170921
|
Interrogatories to Applicant
|
|
2017-09-21
|
2017-09-21
|
EB-2017-0024
|
PRZ-AMPCO-18-Appendix A_20170921
|
Interrogatories to Applicant
|
|
2017-09-21
|
2017-09-21
|
EB-2017-0024
|
AMPCO_IR_Alectra_20170920
|
Interrogatories to Applicant
|
|
2017-09-21
|
2017-09-21
|
EB-2017-0024
|
CCC_IR_Alectra 2018 Rates_20170921
|
Interrogatories to Applicant
|
|
2017-09-21
|
2017-09-21
|
EB-2017-0024
|
VECC_IR_Alectra_20170919
|
Interrogatories to Applicant
|
|
2017-09-20
|
2017-09-20
|
EB-2017-0024
|
BOMA_IR_Alectra_20170920
|
Interrogatories to Applicant
|
|
2017-09-20
|
2017-09-20
|
EB-2017-0024
|
City of Hamilton_IR_Alectra_20170920
|
Interrogatories to Applicant
|
|
2017-09-20
|
2017-09-20
|
EB-2017-0024
|
SEC_IRS_Alectra_20170920
|
Interrogatories to Applicant
|
|
2017-09-19
|
2017-09-19
|
EB-2017-0024
|
PWU_Notice of Appeal_20170918
|
Notice of Appeal
|
|
2017-09-18
|
2017-09-18
|
EB-2017-0024
|
OEB _Reply Ltr_PWU_20170915
|
Correspondence
|
2017-09-15
|
|
2017-09-15
|
EB-2017-0024
|
PO1_Alectra_Revised_20170915
|
Procedural Order
|
2017-09-15
|
|
2017-09-15
|
EB-2017-0024
|
CELPg2_ Intervenor Status Request Denial Review _20170915
|
Correspondence
|
|
2017-09-15
|
2017-09-15
|
EB-2017-0024
|
CELPg1_ Intervenor Status Request Denial Review _20170915
|
Correspondence
|
|
2017-09-15
|
2017-09-15
|
EB-2017-0024
|
PWU_LTR_Alectra_20170912.pdf
|
Correspondence
|
|
2017-09-12
|
2017-09-12
|
EB-2017-0024
|
PO1_Alectra_20170908
|
Procedural Order
|
2017-09-08
|
|
2017-09-08
|
EB-2017-0024
|
PWU_IntrvREQ_20170830
|
Intervenor Request Letter
|
|
2017-08-30
|
2017-08-30
|
EB-2017-0024
|
ALECTRA_LTR_20170829
|
Correspondence
|
|
2017-08-29
|
2017-08-29
|
EB-2017-0024
|
VECC_IntvRqst_20170829
|
Intervenor Request Letter
|
|
2017-08-29
|
2017-08-29
|
EB-2017-0024
|
AMPCO_INTReq_Alectra_20170828
|
Intervenor Request Letter
|
|
2017-08-29
|
2017-08-29
|
EB-2017-0024
|
CCC_IntvRqst_ALECTRA_2018Rates_20170829.pdf
|
Intervenor Request Letter
|
|
2017-08-28
|
2017-08-28
|
EB-2017-0024
|
City of Hamilton_intvRqst_20170828
|
Intervenor Request Letter
|
|
2017-08-28
|
2017-08-28
|
EB-2017-0024
|
BOMA_Correspondence_20170828
|
Correspondence
|
|
2017-08-28
|
2017-08-28
|
EB-2017-0024
|
Affidavit_ Alectra_20170821
|
Affidavits of Service
|
|
2017-08-21
|
2017-08-21
|
EB-2017-0024
|
BOMA_IntREQ_CostEligREQ_20170821
|
Intervenor Request Letter
|
|
2017-08-21
|
2017-08-21
|
EB-2017-0024
|
NoA_ALECTRA_EN_Dated_20170817
|
Notice
|
|
2017-08-18
|
2017-08-18
|
EB-2017-0024
|
NoA_ALECTRA_FR_Dated_20170817
|
Notice
|
|
2017-08-18
|
2017-08-18
|
EB-2017-0024
|
LOD_ALECTRA_IRM_20170817
|
Letter of Direction
|
2017-08-17
|
|
2017-08-17
|
EB-2017-0024
|
AlextraUtilitiesCorp_APPL_Attach50_2018 Enersource_ 20170707
|
Application and Evidence
|
|
|
2017-07-20 at 10:18 AM
|
EB-2017-0024
|
AlectraUtilitiesCorporation_APPL_2018EDR_Attch 46-49_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
SEC_IntvnRqst_20170711
|
Intervenor Request Letter
|
|
2017-07-11
|
2017-07-11
|
EB-2017-0024
|
Ack_ltr__Alectra_10170711
|
Acknowledgement Letter
|
2017-07-11
|
|
2017-07-11
|
EB-2017-0024
|
Capredoni_IntvnRQST_20170710
|
Intervenor Request Letter
|
|
2017-07-10
|
2017-07-10
|
EB-2017-0024
|
Attachment 31 - ICM Model_PowerStream RZ_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 28 - LRAMVA_Work_Form_v 2_PowerStream RZ_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 26 - IRM Model_PowerStream RZ_2017-0707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 11 LRAMVA_Work_Form_v 2_Horizon Utilities RZ_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 10 ESM Rate Rider Model_Horizon Utilties RZ_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 9 RTSR Work Form_Horizon Utilities RZ_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 7 Cost_Allocation 2018_Model_V3_4_Horizon Utilities RZ_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 6b - IRM Model_Horizon Utilities RZ_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 6a- Bill Impacts_Tariff Sheet_Horizon Utilities RZ_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 5 PILs Workform 2017_V1.02_Horizon Utilities RZ_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 4 Revenue Requirement Work Form 2018_V7.02_Horizon Utilties RZ_2017-0707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 45 ICM Model Enersource RZ_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 42 LRAMVA Work Form Enersource RZ_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 39 IRM Model Enersource RZ_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 18 - ICM Model_Brampton RZ_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
Attachment 17 - IRM Model_Brampton RZ_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
AlectraUtilitiesCorporation_APPL_Attach 1-7_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
AlectraUtilitiesCorporation_APPL_Attach52_2018EDR_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
AlectraUtilitiesCorporation_APPL_Attach 51_2018EDR_20170707
|
Application and Evidence
|
|
2017-07-10
|
2017-07-10
|
EB-2017-0024
|
AlectraUtilitiesCorporation_APPL_Attach 42-45_2018EDR_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
AlectraUtilitiesCorporation_APPL_2018EDRAttch 36-41__20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
AlectraUtilitiesCorporation_APPL_2018EDR_Attach 34-35_20170707
|
Application and Evidence
|
|
|
2017-07-07 at 3:37 PM
|
EB-2017-0024
|
AlectraUtilitiesCorporation_APPL_Attach 33_2018EDR_20170707
|
Application and Evidence
|
|
|
2017-07-07 at 3:53 PM
|
EB-2017-0024
|
AlectraUtilitiesCorporation_APPL_Attach 29-32_2018EDR_20170707
|
Application and Evidence
|
|
|
2017-07-07 at 3:53 PM
|
EB-2017-0024
|
AlectraUtilitiesCorporation_APPL_Attach 23-28_2018EDR_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
AlectraUtilitiesCorporation_APPL_Attch 8-10_2018EDR_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
AlectraUtilitiesCorporation_APPL_Attach 11-13_2018EDR_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
AlectraUtilitiesCorporation_APPL_Attach 14-22_2018EDR_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
AlectraUtilitiesCorporation_Tarrif Sheet_Attach 1-7_2018EDR_20170707.pdf
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|
EB-2017-0024
|
AlectraUtilitiesCorporation_APPL_2018EDR_20170707
|
Application and Evidence
|
|
2017-07-07
|
2017-07-07
|